"Commercial Appeals Dismissed: Court Upholds Single Judge's Decision Against Draft Supplemental Agreement" "Arbitral award set aside due to non-execution and unenforceability of central document, with significant procedural and substantive flaws identified."


Summary of Judgement

Two concurrent Commercial Appeals (90 of 2020 and 91 of 2020) arising from an arbitral award dated February 14, 2017. The award was set aside by a Single Judge on January 28, 2020. The appeals involve a dispute regarding a Development Agreement and a Memorandum of Understanding (MoU) dated April 19, 1995, for the development of property owned by the Respondents and to be developed by the Appellant. The central issue is a "draft Supplemental Agreement" asserted by the Appellant but deemed non-existent by the Single Judge. The appeals were dismissed, supporting the Single Judge's finding that the draft Supplemental Agreement was neither executed nor enforceable.

Overview

  • Appeals Overview: Appeals (90 of 2020 and 91 of 2020) stem from an arbitral award dated February 14, 2017, set aside by a Single Judge.
  • Parties Involved: Ivory Properties & Hotels Private Limited (Appellant) and Ms. Bhanumati Jaisukhbhai Bhuta and Ms. Vasantben Ramniklal Bhuta (Respondents).

Agreements and Disputes

  • Development Agreement and MoU: Both dated April 19, 1995, for developing immovable property.
  • Draft Supplemental Agreement: Central to the dispute; asserted by the Appellant but found non-existent and unenforceable by the Single Judge.

Judicial Findings

  • Impugned Judgment: Single Judge set aside the arbitral award, finding it patently illegal and arbitrary.
  • Review Scope: Narrow scope under Section 34 of the Arbitration and Conciliation Act, 1996, without reappreciation of evidence.
  • Existence of Supplemental Agreement: Found non-existent; only a draft with blanks and not executed.

Arbitral Award and Its Flaws

  • Arbitral Award: Concluded that the Development Agreement and MoU were amended by the draft Supplemental Agreement.
  • Single Judge's Findings: Arbitrator failed to meet the basic standard of evidence appreciation; the draft Supplemental Agreement was not a mutually agreed bargain.

Factual Background

  • Original Agreements: Development Agreement and MoU executed on April 19, 1995.
  • Changes and Disputes: Policy changes in 1998 affected the development plans; alleged oral agreement and draft Supplemental Agreement in 1999-2000.

Arbitration Proceedings

  • Invocation of Arbitration: Contested; letter dated February 14, 2002, purportedly invoking arbitration.
  • Arbitral Award: Passed based on flawed conclusions regarding the draft Supplemental Agreement.

Supplemental Agreement Analysis

  • Blanks in Agreement: Critical sections left blank; no specific demarcation of areas or sizes.
  • Judicial Conclusion: Draft Supplemental Agreement not enforceable; gaps and lack of mutual agreement.

Conclusion

  • Appeals Dismissed: Appeals under Section 37 of the Act dismissed, upholding the Single Judge’s judgment.

Contesting the Supplemental Agreement

  • Appellant’s Version: Events including a letter dated February 14, 2002, contested by Respondents.
  • Respondents' Awareness: Claim they only became aware of the letter and the draft Supplemental Agreement in 2009.

Letters from Solicitors and Arbitrator

  • Solicitors’ Letters: Multiple letters to the Sole Arbitrator without mentioning the Supplemental Agreement.
  • Arbitrator's Initial Letters: First letter in 2005 did not reference the Supplemental Agreement.

Arbitrator's Ruling and Issues

  • Conclusion on Agreement: Arbitrator concluded the existence of the Supplemental Agreement without proper adjudication.
  • Perverse Decision: Arbitrator's decision is deemed perverse and contains inherent conflicts.

Cross-Examination and Evidence

  • Witness Testimony: Arbitrator wrongly claimed the Appellant’s witness was not cross-examined on key issues; testimony did not establish a firm date for the Supplemental Agreement.

Arbitrator's Use of Clause 30 and Inchoate Agreement

  • Clause 30: Arbitrator relied on Clause 30 of the Development Agreement but failed to address the incomplete nature of the Supplemental Agreement.

Scope of Interference with Arbitral Awards

  • Limited Scope: Judgment highlights the limited scope for challenging arbitral awards but identifies patent illegality in the Arbitrator’s findings.

Limitation Issue

  • Time-Barred Claim: Found time-barred under the Limitation Act, 1963; breach known in 1995.

Conclusion

  • Appeals Fail: Judgment of the Learned Single Judge is upheld; Arbitrator’s conduct and findings are deemed manifestly arbitrary.

Costs

  • Appellant’s Costs: Directed to pay costs of Rs. 40,00,000/- to the Respondents within four weeks.
  • Stay on Costs: Stay on payment of costs granted for eight weeks to allow the Appellant to challenge the order before the Supreme Court.

Case Title: Ivory Properties & Hotels Private Limited Versus Vasantben Ramniklal Bhuta Ors.

Citation: 2024 Lawtext (BOM) (6) 252

Case Number: COMMERCIAL APPEAL NO. 90 OF 2020 IN COMMERCIAL ARBITRATION PETITION NO. 812 OF 2019 WITH COMMERCIAL APPEAL NO. 91 OF 2020 IN COMMERCIAL ARBITRATION PETITION NO. 350 OF 2017

Advocate(s): Mr.Rohit Kapadia, Senior Advocate a/w. Yash Kapadia, Hemlata Jain, Kaiwan Kalyaniwalla, Sanidhaa Vedpathak, Nijam-S-Sher S. Sani, Pooja Shah and Nirav Barot i/b Maneksha & Sethna, Mr.Shailesh Shah, Senior Advocate a/w. Dibyajyoti Banerji, Aditya Udeshi, Netaji Gawade and Nayan Bhalekar i/b M/s. Sanjay Udeshi & Co., Mr.T.N. Subramaniam, Senior Advocate a/w. Rubin Vakil, Nupur Desai i/b M/s. Markand Gandhi & Co.

Date of Decision: 2024-06-25