Case Note & Summary
The petitioner, M/s DRN Infrastructure Pvt. Ltd., a company registered under the Companies Act, 2013, was awarded a contract by the South Western Railway for construction work. The Railway issued a termination notice dated 18.08.2025 terminating the contract without any prior show cause notice or opportunity of hearing. The petitioner challenged the termination by filing two writ petitions under Article 226 of the Constitution of India, seeking quashing of the termination notice and other consequential reliefs. The main legal issue was whether the termination was valid in the absence of compliance with the contractual requirement of a show cause notice and the principles of natural justice. The petitioner argued that the termination was arbitrary and in breach of the contract terms. The respondents, represented by the Assistant Solicitor General of India, contended that the termination was justified due to the petitioner's poor performance. The court analyzed the contractual clauses and found that the contract mandated a pre-termination notice and an opportunity to show cause, which were not followed. The court held that the termination was in violation of natural justice and the contractual terms, and therefore, quashed the termination notice. The court directed the respondents to issue a show cause notice and consider the petitioner's explanation before taking any further action. The judgment favored the petitioner.
Headnote
A) Contract Law - Termination of Contract - Breach of Natural Justice - The Railway terminated the contract without issuing a show cause notice or giving an opportunity of hearing to the contractor, which is a violation of the principles of natural justice and the contractual terms requiring a pre-termination notice. Held that the termination is unsustainable and quashed. (Paras 1-10) B) Constitutional Law - Writ Jurisdiction - Article 226 of the Constitution of India - The High Court can interfere with a termination order that is arbitrary and in violation of natural justice, even in contractual matters, when the action is without jurisdiction or in breach of statutory or contractual obligations. (Paras 1-10)
Issue of Consideration
Whether the termination of a contract by the Railway without issuing a show cause notice and without considering the contractor's explanation is valid and in accordance with the principles of natural justice and the terms of the contract.
Final Decision
The court quashed the termination notice dated 18.08.2025 and directed the respondents to issue a show cause notice and consider the petitioner's explanation before taking any further action.
Law Points
- Natural justice
- Contractual pre-conditions
- Termination of contract
- Show cause notice
- Writ jurisdiction under Article 226



