Case Note & Summary
The appeals arose from orders of the National Consumer Disputes Redressal Commission (NCDRC) allowing a revision petition by Haryana State Industrial Development Corporation (HSIDC) regarding the resumption of an industrial plot. The appellant, a proprietary concern, applied for an industrial plot in 1994, received a letter of intent, and was allotted Plot No. 182-M in Udyog Vihar, Gurgaon, with possession handed over in 1995. The allotment agreement required completion of the project within two years. The appellant failed to construct or start production, citing lack of infrastructural facilities such as electricity and roads, and requested extensions. HSIDC issued multiple show-cause notices in 1996, 1998, and 1998, but the appellant did not demonstrate substantial progress. In 1998, HSIDC resumed the plot and refunded the payment, which the appellant rejected. The appellant filed a complaint with the District Consumer Forum, which ruled in his favor, but HSIDC appealed. The State Commission dismissed the appeal, and the NCDRC initially dismissed HSIDC's revision petition on delay grounds. The Supreme Court remanded the matter, and the NCDRC, after remand, allowed HSIDC's revision, finding the appellant's reasons vague and evasive. The legal issues involved whether HSIDC's resumption was justified due to non-compliance with allotment terms and whether principles of natural justice were violated. The appellant argued that he took steps like obtaining certificates and applying for connections, but policy changes and lack of infrastructure hindered him, and that HSIDC acted without a hearing. HSIDC contended that sufficient opportunity was given, and the appellant showed no interest in industrial activity, possibly speculating on land value. The court analyzed the record, noting the appellant's persistent inaction despite opportunities and the agreement's conditions, particularly Clause 6. It found that the appellant did not take concrete steps, and HSIDC's actions were justified. The court held that there was no violation of natural justice as show-cause notices provided adequate opportunity. The Supreme Court dismissed the appeals, upholding the NCDRC's decision that HSIDC was justified in resuming the plot due to the appellant's failure to fulfill the allotment conditions.
Headnote
A) Consumer Law - Industrial Plot Allotment - Resumption for Non-Compliance - Consumer Protection Act, 1986 - The appellant, an allottee of an industrial plot, failed to construct and start production within the stipulated time despite multiple show-cause notices and extensions - The NCDRC held that the appellant's reasons were vague and evasive, and HSIDC was justified in resuming the plot under Clause 6 of the agreement - The Supreme Court upheld this, finding no violation of natural justice as sufficient opportunity was given (Paras 1-16). B) Contract Law - Allotment Agreement - Terms and Conditions - Not mentioned - The dispute centered on Clause 6 of the allotment agreement, which required the allottee to start construction and set up the unit within two years - The appellant alleged lack of infrastructural facilities hindered compliance, but the court found no concrete steps taken by the appellant - Held that HSIDC's resumption was valid due to persistent inaction and failure to meet contractual obligations (Paras 13-16). C) Administrative Law - Natural Justice - Hearing and Reasoned Orders - Not mentioned - The appellant argued that HSIDC violated principles of natural justice by not granting a hearing and issuing a non-speaking resumption order - The court noted that multiple show-cause notices were issued, and the appellant had opportunities to respond - Held that there was no violation as sufficient procedural fairness was afforded (Paras 15-16).
Issue of Consideration
Whether the resumption of the industrial plot by HSIDC was justified due to the appellant's failure to fulfill the terms and conditions of allotment, and whether principles of natural justice were violated in the resumption process
Final Decision
The Supreme Court dismissed the appeals, upholding the NCDRC's decision that HSIDC was justified in resuming the plot due to the appellant's failure to fulfill the allotment conditions, and found no violation of principles of natural justice
Law Points
- Principles of natural justice
- compliance with contractual terms
- consumer protection
- resumption of industrial plots for non-fulfillment of conditions
- interpretation of allotment agreements





