Case Note & Summary
The Supreme Court heard an appeal by the Government of NCT of Delhi against a High Court judgment that declared land acquisition proceedings had lapsed under Section 24(2) of the 2013 Act. The dispute concerned acquisition of land where possession of 19 biswa out of 20 was taken in 2009, with the remaining 1 biswa not taken due to built-up structures. The Land Acquisition Collector issued a notice under Section 12(2) of the 1894 Act in 2009, but when the landowner did not collect compensation, it was sent to revenue deposit. The High Court had allowed the writ petition based on Pune Municipal Corporation precedent, requiring categorical proof of compensation payment. The Supreme Court identified the core legal issue as whether the acquisition had lapsed under Section 24(2) given these facts. The appellants argued that possession was substantially taken and compensation was properly tendered, while the respondent presumably contended that non-payment caused lapse. The Court analyzed the Constitution Bench decision in Indore Development Authority which overruled Pune Municipal Corporation and established that Section 24(2) requires both possession not taken AND compensation not paid for lapse to occur. The Court reasoned that since possession of the major portion was taken through proper proceedings and compensation was tendered via notice, the landowner's refusal to collect it did not constitute non-payment. The Court emphasized that landowners cannot benefit from their own refusal to accept compensation. Applying Indore Development Authority, the Court held the acquisition had not lapsed, quashed the High Court's judgment, and dismissed the original writ petition, thereby upholding the acquisition proceedings.
Headnote
A) Land Acquisition - Deemed Lapse of Proceedings - Section 24(2) of Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 - The Supreme Court examined whether acquisition proceedings had lapsed under Section 24(2) where possession of major portion was taken and compensation notice was issued but not collected - Court applied Indore Development Authority which overruled Pune Municipal Corporation and held that lapse requires both possession not taken AND compensation not paid - Since possession of 19 biswa out of 20 was taken and compensation notice was served, no lapse occurred (Paras 1-5). B) Land Acquisition - Compensation Payment - Sections 12(2), 31(1) of Land Acquisition Act, 1894 - The Court considered whether non-collection of compensation by landowner after proper notice constitutes non-payment under Section 24(2) - Held that when notice under Section 12(2) was issued and served but landowner did not collect compensation, sending it to revenue deposit fulfills obligation - Landowner cannot benefit from own conduct by refusing to collect compensation (Paras 3-4). C) Land Acquisition - Precedent Application - Overruling of Pune Municipal Corporation - The High Court had relied on Pune Municipal Corporation which required categorical statement of compensation payment - Supreme Court noted this precedent was overruled by Constitution Bench in Indore Development Authority - The correct legal position requires reading 'or' in Section 24(2) as 'nor' meaning both conditions must fail for lapse (Paras 2.1-3).
Issue of Consideration
Whether the acquisition proceedings with respect to the land in question are deemed to have lapsed under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013
Final Decision
The appeal succeeds. The impugned judgment and order passed by the High Court is quashed and set aside. The original writ petition before the High Court stands dismissed. There shall be no deemed lapse of the acquisition with respect to the land in question under Section 24(2) of the Act, 2013. The appeal is allowed with no costs.
Law Points
- Interpretation of Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition
- Rehabilitation and Resettlement Act
- 2013
- deemed lapse of land acquisition proceedings
- possession taking under Land Acquisition Act
- 1894
- compensation payment requirements
- overruling of Pune Municipal Corporation precedent



