Case Note & Summary
The appeal was filed under Section 125 of the Electricity Act, 2003, challenging the Appellate Tribunal for Electricity's judgment that dismissed the appellant's appeal. The appellant, an Independent Power Producer operating a gas turbine power station in Tamil Nadu, had initially filed a petition under Section 86(1)(f) of the Electricity Act, 2003, before the Tamil Nadu Electricity Regulatory Commission, seeking payment of fixed and variable charges for periods affected by shortage of gas supply, alleging diversion of gas to other generating stations by the Tamil Nadu Electricity Board. The Commission rejected the claims, and the Tribunal upheld this, finding no provision in the Power Purchase Agreement dated 25 August 2004 or Tariff Regulations for compensation due to fuel shortage. The appellant argued before the Supreme Court that the Tribunal erred in not considering evidence of gas diversion and that payment should be made on quantum meruit principles, citing precedents. The respondents contended that the PPA was not approved under Section 86(1)(b) of the Act, there was no compensation clause, and fuel supply risk was on the appellant per a Government notification. The Court analyzed the facts, noting the PPA's lack of approval and absence of clauses for compensation or indemnity for gas shortage. It referenced the Government notification placing fuel linkage responsibility on the independent power producer and found no provision in the Act or PPA protecting the appellant's rights. The Court rejected the quantum meruit argument, as the PPA was binding inter se and no default by the Board was established. The decision affirmed the Tribunal's dismissal, holding the appellant not entitled to compensation for fixed and variable charges during the gas shortage period.
Headnote
A) Electricity Law - Power Purchase Agreement - Compensation for Fuel Shortage - Electricity Act, 2003, Sections 86(1)(b), 86(1)(f), 125 - Appellant sought payment of fixed and variable charges for period affected by gas shortage - Court found no provision in PPA or Tariff Regulations for compensation due to fuel shortage, and PPA was not approved under Section 86(1)(b) - Held that appellant not entitled to compensation as fuel supply risk lies with independent power producer per Government notification (Paras 15-18). B) Contract Law - Quantum Meruit - Applicability to Unapproved Agreement - Electricity Act, 2003 - Appellant argued for payment on quantum meruit basis since electricity was sold - Court rejected argument as PPA was binding inter se and no clause provided for compensation, and principle not applicable in absence of approval under Act - Held that Board not liable to pay compensation for fuel shortage issues (Paras 8-9, 16).
Issue of Consideration
Whether the appellant is entitled to payment of fixed and variable charges for the period when operational parameters were affected due to shortage of gas supply, despite absence of provision in the PPA or Tariff Regulations.
Final Decision
The Supreme Court dismissed the appeal, upholding the Tribunal's judgment that the appellant is not entitled to payment of fixed and variable charges for the period affected by gas shortage, as there is no provision in the PPA or Tariff Regulations for such compensation.
Law Points
- Interpretation of Power Purchase Agreement
- absence of compensation clause for fuel shortage
- non-approval of PPA under Electricity Act
- 2003
- principle of quantum meruit not applicable
- fuel supply risk on independent power producer





