Supreme Court Allows Appeal by MSEDCL in Electricity Tariff Dispute Over Change in Law Due to Wildlife Notification. Held that the notification declaring buffer zone around Tadoba Tiger Reserve constituted a 'Change in Law' under PPAs, entitling APML to compensatory tariff for all four PPAs.

  • 6
Judgement Image
Font size:
Print

Case Note & Summary

The present appeals arise from a dispute between Maharashtra State Electricity Distribution Company Limited (MSEDCL), the appellant, and Adani Power Maharashtra Limited (APML), respondent No. 1, concerning the interpretation of 'Change in Law' provisions in four long-term Power Purchase Agreements (PPAs) entered into between them. The PPAs were executed on 8th September 2008 (1230 MW), 21st March 2010 (1200 MW), 9th August 2010 (120 MW), and 16th February 2013 (440 MW), following a competitive bidding process. Prior to the PPAs, APML had applied for and received allocation of Lohara Coal Blocks from the Ministry of Coal on 6th November 2007. On 27th December 2007, the Government of Maharashtra issued a notification under Section 38(V) of the Wild Life (Protection) Act, 1972, declaring a Critical Tiger Habitat (CTH) covering 625.82 sq. km. of Tadoba National Park and Andheri Wildlife Sanctuary. At that time, the CTH did not include the Lohara Coal Blocks area. APML submitted its bid on 21st February 2008, with a cut-off date of 14th February 2008, specifying the Lohara Coal Blocks as the fuel source for 800 MW out of 1320 MW. After the cut-off date, on 21st February 2008, the Conservator of Tadoba Andheri Tiger Reserve approved the constitution of an Expert Committee for creating a Buffer Zone around the core area. The legal issue is whether the notification and subsequent buffer zone creation constitute a 'Change in Law' under the PPAs, entitling APML to compensatory tariff. MSEDCL argued that the notification was issued before the bid deadline and thus was not a Change in Law, while APML contended that the notification and buffer zone impacted coal mining, making it a Change in Law. The Maharashtra Electricity Regulatory Commission (MERC) rejected APML's claim, but the Appellate Tribunal for Electricity (APTEL) allowed the appeal in part, holding that the notification was a Change in Law but only for the 1230 MW PPA. The Supreme Court, in its analysis, held that the notification dated 27th December 2007 was a Change in Law as it was issued after the bid cut-off date and affected coal mining operations. The Court further held that the Change in Law impacted all four PPAs, as the coal blocks were the designated fuel source for a portion of the capacity under each PPA. The Supreme Court allowed MSEDCL's appeal in part, setting aside APTEL's restriction to the 1230 MW PPA, and remanded the matter to MERC for determination of the exact compensation for all PPAs.

Headnote

A) Electricity Law - Change in Law - Power Purchase Agreement - The notification under Section 38(V) of the Wild Life (Protection) Act, 1972 declaring a Critical Tiger Habitat and the subsequent creation of a buffer zone constitute a 'Change in Law' event under the PPAs, as the notification was issued after the bid cut-off date and impacted coal mining operations. Held that the Appellate Tribunal for Electricity (APTEL) correctly held that the notification dated 27th December 2007 was a Change in Law, but erred in restricting compensation to only the 1230 MW PPA. (Paras 1-6)

B) Electricity Law - Tariff Determination - Compensatory Tariff - The Supreme Court held that the Change in Law event affected all four PPAs (1230 MW, 1200 MW, 120 MW, and 440 MW) as the coal blocks were the designated fuel source for a portion of the capacity under each PPA. Held that APML is entitled to compensatory tariff for all PPAs, and the matter is remanded to MERC for determination of the exact compensation. (Paras 2-6)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the notification dated 27th December 2007 declaring a Critical Tiger Habitat and the subsequent creation of a buffer zone around Tadoba Andheri Tiger Reserve constitute a 'Change in Law' under the Power Purchase Agreements between MSEDCL and APML, entitling APML to compensatory tariff.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Supreme Court allowed the appeals in part, setting aside the APTEL order to the extent it restricted the Change in Law to the 1230 MW PPA. The Court held that the Change in Law event affected all four PPAs and remanded the matter to MERC for determination of the exact compensation for all PPAs.

Law Points

  • Change in Law
  • Force Majeure
  • Electricity Tariff
  • Power Purchase Agreement
  • Regulatory Commission
  • Appellate Tribunal for Electricity
Subscribe to unlock Law Points Subscribe Now

Case Details

2023 LawText (SC) (4) 97

Civil Appeal Nos. 1234-1235 of 2021

2021-08-27

B.R. Gavai, J.

Maharashtra State Electricity Distribution Company Limited (MSEDCL)

Adani Power Maharashtra Limited (APML) and others

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Appeal against order of Appellate Tribunal for Electricity (APTEL) regarding interpretation of 'Change in Law' in Power Purchase Agreements.

Remedy Sought

MSEDCL sought to set aside APTEL's order allowing compensatory tariff to APML; APML sought to expand the scope of compensation to all four PPAs.

Filing Reason

Dispute over whether a wildlife notification and buffer zone creation constituted a 'Change in Law' under the PPAs.

Previous Decisions

MERC rejected APML's claim; APTEL allowed appeal in part, holding Change in Law only for 1230 MW PPA.

Issues

Whether the notification dated 27th December 2007 and subsequent buffer zone creation constitute a 'Change in Law' under the PPAs. Whether the Change in Law affects all four PPAs or only the 1230 MW PPA.

Submissions/Arguments

MSEDCL argued that the notification was issued before the bid deadline and thus not a Change in Law. APML contended that the notification and buffer zone impacted coal mining, making it a Change in Law affecting all PPAs.

Ratio Decidendi

A notification under the Wild Life (Protection) Act issued after the bid cut-off date but before the bid deadline constitutes a 'Change in Law' under the PPAs, and such change affects all PPAs that rely on the affected coal blocks as a fuel source.

Judgment Excerpts

The present appeals challenge the judgment and order dated 5th October 2020 passed by the Appellate Tribunal for Electricity... APML and MSEDCL had entered into four long term Power Project Agreements... Prior to the signing of the PPAs... APML had applied to the Ministry of Coal... for allotment of Lohara Coal Blocks... On 27th December 2007, the Government of Maharashtra issued a statutory Notification under Section 38(V) of the Wild Life (Protection) Act, 1972... Twenty-four days after the bid cut-off date, the Conservator of the Tadoba Andheri Tiger Reserve approved the constitution of an Expert Committee for the creation of a Buffer Zone...

Procedural History

MERC rejected APML's claim for compensatory tariff. APML appealed to APTEL, which allowed the appeal in part, holding Change in Law only for the 1230 MW PPA. Both MSEDCL and APML appealed to the Supreme Court.

Acts & Sections

  • Wild Life (Protection) Act, 1972: Section 38(V)
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Allows Appeal by MSEDCL in Electricity Tariff Dispute Over Change in Law Due to Wildlife Notification. Held that the notification declaring buffer zone around Tadoba Tiger Reserve constituted a 'Change in Law' under PPAs, entitling APML...
Related Judgement
Supreme Court Supreme Court Clarifies High Court's Writ Jurisdiction Over Armed Forces Tribunal Orders in Service Matters. The court held that orders of the Armed Forces Tribunal are amenable to challenge under Article 226 of the Constitution, as judicial review i...