Case Note & Summary
The appellant, The Madras Aluminium Co. Ltd., a company established in 1965 for manufacturing aluminium, was declared a sick industrial unit under Section 3(1)(O) of the Sick Industrial Companies Act, 1985 by the Board for Industrial and Financial Reconstruction on 8th September 1987. In 1994, the new management approached the Board for revival. The appellant had an electricity supply agreement with the respondent, Tamil Nadu Electricity Board, for a contracted load of 23000 KVA. Due to reduced operations, the appellant applied for reduction of the contracted load to 10000 KVA. The respondent took considerable time to process the application and enter into a revised agreement. During this period, the appellant continued to pay demand charges based on 23000 KVA under protest. The appellant filed writ petitions before the Madras High Court seeking refund of the excess amount paid. A learned Single Judge dismissed the petitions, holding that the appellant was bound to pay charges as per the contract irrespective of consumption. The Division Bench in writ appeal upheld the Single Judge's order, holding that such a dispute is not one to be adjudicated under Article 226 of the Constitution of India. The appellant then appealed to the Supreme Court. The Supreme Court considered whether the respondent's delay in processing the load reduction application was arbitrary and unreasonable, and whether the appellant was entitled to refund of the difference in demand charges paid under protest. The Court allowed the appeals, holding that the delay was unreasonable and the appellant was entitled to refund.
Headnote
A) Electricity Law - Contractual Obligation - Demand Charges - Delay in Load Reduction - The issue was whether the Electricity Board's delay in processing the application for reduction of contracted load from 23000 KVA to 10000 KVA was arbitrary and unreasonable. The Court held that the Board's inordinate delay was unreasonable, and the consumer was entitled to refund of excess demand charges paid under protest during the period of delay. (Paras 1-4) B) Constitutional Law - Writ Jurisdiction - Article 226 - Contractual Disputes - The High Court had held that the dispute regarding demand charges under an electricity supply agreement was not amenable to writ jurisdiction under Article 226 of the Constitution of India. The Supreme Court did not specifically rule on this point but allowed the appeals on merits. (Para 3)
Issue of Consideration
Whether the action of the Respondent in taking considerable time from when the application was made for reduction to 10000 KVA, to when the revised agreement was entered into, was arbitrary and unreasonable; and whether the Appellant is entitled to refund of the amount of difference between the amounts payable for 23000 KVA and 10000 KVA which have been paid under protest.
Final Decision
The Supreme Court allowed the appeals, holding that the respondent's delay in processing the load reduction application was unreasonable, and the appellant is entitled to refund of the excess demand charges paid under protest.
Law Points
- Contractual obligation
- Unreasonable delay
- Refund of excess charges
- Electricity supply agreement
- Demand charges
- Load reduction


