Supreme Court Allows Appeal by MP Power Management Company, Upholds Termination of Power Purchase Agreement for Non-Compliance of Conditions Subsequent. The Court held that the High Court erred in interfering with a non-statutory contract and that the termination was justified as the seller failed to fulfill conditions within the extended period.

  • 8
Judgement Image
Font size:
Print

Case Note & Summary

The appellant, M.P. Power Management Company Limited, a wholly owned government company responsible for bulk purchase of electricity in Madhya Pradesh, issued a request for proposal for procurement of 300 MW solar energy. The bid of M/s Sky Power Southeast Asia Holding Limited was accepted, and it incorporated the first respondent as a special purpose company for a 50 MW project. A Power Purchase Agreement was executed on 18.09.2015, with a tariff of Rs.5.109 per unit. The PPA required the seller to fulfill conditions subsequent within 210 days, i.e., by 15.04.2016, with an extension of nine months on payment of penalty, making the final deadline 15.01.2017. The first respondent failed to comply within this period. On 12.01.2017, it submitted documents claiming compliance, but the appellant found deficiencies, including lack of land documents and financial closure. After correspondence, the appellant issued a termination notice on 11.08.2017. The first respondent challenged this in Writ Petition No. 12880 of 2017, which was allowed by the High Court on 20.06.2018, relying on a similar case (Renew Clean Energy Private Limited) where termination for delay in first milestone was set aside. The High Court set aside the termination but granted liberty to pass fresh orders. Consequently, the appellant issued a fresh termination order on 07.07.2018, which was challenged in Writ Petition No. 420 of 2019. The High Court again set aside the termination on 27.02.2020, and dismissed the review on 28.12.2020. The Supreme Court, after hearing arguments, held that the writ petition was not maintainable as the PPA was a non-statutory contract, and the remedy lay in civil suit or arbitration. The Court also found that the first respondent had failed to fulfill conditions subsequent within the extended period, and the termination was justified. The earlier judgment in Renew Clean Energy was distinguishable as in that case the project was commissioned, whereas here it was not. The Supreme Court allowed the appeals, set aside the impugned orders, and dismissed the writ petition, leaving the parties to seek remedies in accordance with law.

Headnote

A) Constitutional Law - Maintainability of Writ Petition - Non-Statutory Contract - A writ petition under Article 226 is not maintainable against termination of a non-statutory contract, as the remedy lies in civil suit or arbitration. The High Court erred in entertaining the writ petition challenging the termination of the Power Purchase Agreement, which was a commercial contract. (Paras 10-12)

B) Contract Law - Conditions Subsequent - Power Purchase Agreement - Fulfillment of Conditions Subsequent - The seller failed to fulfill conditions subsequent within the stipulated period of 210 days plus extended period of 9 months, i.e., by 15.01.2017. The termination was justified under Article 2.5.1(d) of the PPA. (Paras 3-7)

C) Precedent - Res Judicata - Previous Judgment on Similar Facts - The earlier judgment in Renew Clean Energy Private Limited case, which set aside termination for delay in first milestone, was not applicable as the facts were different. In that case, the project was commissioned, whereas here the project was not commissioned. (Paras 7-8)

D) Electricity Law - Power Purchase Agreement - Termination - Section 162 of the Electricity Act, 2003 - The approval obtained from CEIG under Regulation 32 of CEA Regulations was not a valid fulfillment of conditions subsequent as it was obtained after the expiry of the extended period. (Para 7)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the High Court was justified in setting aside the termination of the Power Purchase Agreement by the appellant on the ground of non-fulfillment of conditions subsequent by the first respondent, and whether the writ petition was maintainable against a non-statutory contract.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Supreme Court allowed the appeals, set aside the impugned judgments of the High Court dated 27.02.2020 and 28.12.2020, and dismissed the writ petition filed by the first respondent. The parties are left to seek remedies in accordance with law.

Law Points

  • Maintainability of writ petition against termination of non-statutory contract
  • Interpretation of conditions subsequent in Power Purchase Agreement
  • Effect of previous judgment on similar facts
  • Doctrine of merger
  • Res judicata
Subscribe to unlock Law Points Subscribe Now

Case Details

2022 LawText (SC) (11) 13

Civil Appeal Nos. _________ of 2022 (Arising out of SLP (C) Nos. 4609-4610 of 2021)

2022-01-01

K.M. Joseph

M.P. Power Management Company Limited, Jabalpur

M/s. Sky Power Southeast Solar India Private Limited & Others

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Civil appeals against High Court judgment setting aside termination of Power Purchase Agreement.

Remedy Sought

Appellant sought to set aside the High Court's judgment allowing the writ petition and quashing the termination order.

Filing Reason

The appellant terminated the PPA due to non-fulfillment of conditions subsequent by the first respondent within the stipulated period.

Previous Decisions

High Court in Writ Petition No. 12880 of 2017 set aside earlier termination on 20.06.2018, granting liberty to pass fresh orders. Fresh termination order dated 07.07.2018 was set aside by High Court on 27.02.2020, and review dismissed on 28.12.2020.

Issues

Whether the writ petition challenging termination of a non-statutory contract is maintainable. Whether the termination of the PPA by the appellant was justified due to non-fulfillment of conditions subsequent by the first respondent.

Submissions/Arguments

Appellant argued that the PPA is a non-statutory contract, hence writ petition not maintainable; remedy lies in civil suit or arbitration. Also, the first respondent failed to fulfill conditions subsequent within the extended period, justifying termination. First respondent argued that the High Court correctly set aside termination, relying on earlier judgment in Renew Clean Energy case, and that conditions were substantially complied with.

Ratio Decidendi

A writ petition under Article 226 is not maintainable against termination of a non-statutory contract. The Power Purchase Agreement was a commercial contract, and the seller failed to fulfill conditions subsequent within the extended period, justifying termination. The earlier judgment in Renew Clean Energy was distinguishable as the project was commissioned there, unlike here.

Judgment Excerpts

The appellant impugns the Judgment of the High Court dated 27.02.2020 in Writ Petition No. 420 of 2019. The Agreement contemplated completion of the conditions subsequent, within a period of 210 days. The High Court allowed the Writ Petition filed by the first respondent and quashed the Order dated 07.07.2018.

Procedural History

The appellant terminated the PPA on 11.08.2017. First respondent filed Writ Petition No. 12880 of 2017, which was allowed on 20.06.2018, setting aside termination with liberty to pass fresh orders. Appellant issued fresh termination on 07.07.2018. First respondent filed Writ Petition No. 420 of 2019, which was allowed on 27.02.2020. Review Petition No. 682 of 2020 was dismissed on 28.12.2020. Appellant filed SLP (C) Nos. 4609-4610 of 2021, which were converted into Civil Appeals and allowed by Supreme Court.

Acts & Sections

  • Electricity Act, 2003: 162
  • Central Electricity Authority (Measures relating to safety and electricity supply) Regulations, 2010: 32
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Allows Appeal by MP Power Management Company, Upholds Termination of Power Purchase Agreement for Non-Compliance of Conditions Subsequent. The Court held that the High Court erred in interfering with a non-statutory contract and that th...
Related Judgement
Supreme Court "Supreme Court Upholds Sanction and Cognizance Under UAPA: Fuleshwar Gope vs Union of India" "Sanction Validity and Cognizance Under UAPA: No Procedural Infirmities, Trial to Continue"