Case Note & Summary
The dispute arose from a road construction contract under the Special Accelerated Rural Development Programme (SARDP) for improvement of road from Lumla to Tashigong. The respondent contractor, M/s Puna Hinda, was awarded the work through a Notice Inviting Tender issued on 22.10.2008, with a work order on 15.7.2009, later amended on 15.3.2012. The contract included General Conditions specifying measurement methods for excavation work. The contractor completed formation work by 20.9.2012, and a joint survey was conducted by a Board of Officers on 23.1.2013, recommending quantities for payment based on theoretical calculations pending final survey. A Final Joint Survey/Measurement Report dated 24.10.2013 was prepared, but the appellants rejected it via letters dated 27.8.2015 and 21.10.2015, demanding a resurvey. The contractor filed a writ petition seeking quashing of these letters and payment of Rs. 31,57,16,134/- with interest. The Single Bench of Gauhati High Court allowed the petition, directing payment based on the final joint survey report within four months. The Division Bench dismissed the intra-court appeal, noting that five monsoons had passed, making a resurvey unjust. The core legal issues were whether the High Court erred in relying on the final joint survey report and whether the appellants' rejection was valid. The appellants argued for a resurvey, while the respondent contended the report was binding. The court analyzed the contractual terms, particularly Clause 2.8.1, and held that the joint survey report was final and should form the basis for payment, as it was conducted as per contract specifications. The court affirmed the High Court's decision, dismissing the appeal and upholding the payment direction. The final decision favored the contractor, with the court emphasizing the finality of the survey report and the impracticality of a resurvey after significant time had elapsed.
Headnote
A) Contract Law - Government Contracts - Measurement and Payment - General Conditions of Contract, Clause 2.8.1 - Dispute pertained to measurement of excavation work for road construction under SARDP - High Court directed payment based on Final Joint Survey Report dated 24.10.2013, rejecting appellants' demand for resurvey - Held that the joint survey report was final and binding, and payment must be made accordingly as per contractual terms (Paras 1-4). B) Administrative Law - Judicial Review - Quashing of Administrative Letters - Not mentioned - Writ petitioner sought quashing of letters dated 27.8.2015 and 21.10.2015 which rejected payment claims - High Court allowed the writ petition, quashing the letters and directing payment - Held that the administrative rejection was unjustified as it contradicted the final joint survey report (Paras 2-3). C) Civil Procedure - Appeals - Intra-court Appeal Dismissal - Not mentioned - Division Bench of Gauhati High Court dismissed intra-court appeal, affirming Single Bench order - Supreme Court considered challenge to this dismissal - Held that the High Court's decision was correct, and the appeal was dismissed (Paras 1-4).
Issue of Consideration
Whether the High Court erred in directing payment to the contractor based on the Final Joint Survey/Measurement Report dated 24.10.2013, and whether the appellants were justified in rejecting the report and demanding a resurvey.
Final Decision
The Supreme Court dismissed the appeal, upholding the High Court's order directing payment to the respondent based on the Final Joint Survey/Measurement Report dated 24.10.2013, with the Division Bench's reasoning that a resurvey would not be just after five monsoons.
Law Points
- Contractual interpretation
- measurement of work under General Conditions of Contract
- finality of joint survey reports
- judicial review of administrative decisions
- payment obligations under government contracts



