Case Note & Summary
The dispute arose from an agreement dated 30 August 1979 between the State of Madhya Pradesh and M/s Sal Udyog Private Limited for the supply of Sal seeds, renewed on 30 April 1992. The State terminated the agreement in 1998 under the M.P. Van Upaj Ke Kararon Ka Punarikshan Adhiniyam, 1987. The respondent invoked arbitration, claiming refund of excess payments, including supervision charges. The Arbitral Award dated 17 February 2005 allowed the claim, awarding Rs. 7,43,46,772 with interest, and disallowed supervision charges of Rs. 1.49 crores. The State filed a petition under Section 34 of the Arbitration and Conciliation Act, 1996, which was partially modified by the District Judge on 14 March 2006, reducing the interest period. Both parties appealed under Section 37 to the Chhattisgarh High Court, which in a common judgment dated 21 October 2009 modified the interest rate from 18% to 9% per annum and dismissed the respondent's cross-appeal. The Supreme Court granted leave limited to the issue of disallowance of supervision charges. The State argued that the Award was patently illegal as supervision charges were contractually agreed and paid without objection, citing Delhi Airport Metro Express. The respondent contended that the State waived this objection by not raising it in the Section 34 petition, relying on State of Maharashtra v. Hindustan Construction. The Court analyzed the contract terms, Arbitrator's reasoning, and precedents. It held that the Arbitrator's interpretation of the contract, based on evidence and guidelines, did not constitute patent illegality, and judicial interference under Section 34 is limited. The Court also rejected the waiver argument, noting the objection was taken before the Arbitrator and in the Section 37 appeal, and waiver cannot be inferred from omission in the Section 34 petition as per Lion Engineering Consultants. The appeal was dismissed, upholding the Award's disallowance of supervision charges.
Headnote
A) Arbitration Law - Judicial Interference - Patent Illegality - Arbitration and Conciliation Act, 1996, Sections 34, 37 - The Supreme Court examined whether the Arbitral Award's disallowance of supervision charges constituted a patent illegality warranting interference under Section 34. The Court held that the Arbitrator's interpretation of the contract terms, based on evidence and guidelines, did not reveal any perversity or fundamental error, and thus the Award was not patently illegal. The Court emphasized limited scope of judicial review in arbitration matters. (Paras 12-15) B) Arbitration Law - Waiver of Objections - Grounds in Section 34 Petition - Arbitration and Conciliation Act, 1996, Sections 34, 37 - The respondent argued that the State waived its right to challenge the supervision charges issue by not raising it in the Section 34 petition. The Court rejected this, noting that the objection was taken before the Arbitrator and in the Section 37 appeal, and waiver cannot be inferred merely from omission in the Section 34 petition, as per precedent in Lion Engineering Consultants. (Paras 10-11, 14)
Issue of Consideration
Whether the High Court erred in not interfering with the Arbitral Award that disallowed supervision charges claimed by the State, and whether the State's objection was waived due to not raising it in the Section 34 petition.
Final Decision
The Supreme Court dismissed the appeal, upholding the Arbitral Award's disallowance of supervision charges. The Court found no patent illegality in the Arbitrator's interpretation and rejected the waiver argument.
Law Points
- Arbitration and Conciliation Act
- 1996
- Section 34
- Section 37
- patent illegality
- scope of judicial interference
- waiver of objections
- interpretation of contract terms



