Supreme Court Dismisses Appeals of Generating Company and State Utility in Electricity Tariff Dispute. Deemed Generation Incentive Not Payable After 1995 Notification; Supplementary Agreement Bars Retrospective Interest on Deemed Loan.

  • 9
Judgement Image
Font size:
Print

Case Note & Summary

The Supreme Court dismissed two appeals arising from a common order of the Appellate Tribunal for Electricity (APTEL) concerning a power purchase agreement (PPA) between CLP India Pvt. Ltd. (a generating company) and Gujarat Urja Vikas Nigam Ltd. (the state utility). The PPA, dated 03.02.1994, obligated Gujarat Urja to purchase 635 MW of electricity from CLP for 20 years. The tariff was governed by a Central Government notification under Section 43A of the Electricity Supply Act, 1948, which initially provided for an incentive for generation above a target availability. However, an amendment notification dated 06.11.1995 capped the deemed generation incentive for naphtha-based plants. Despite this, CLP continued to bill for the incentive, and Gujarat Urja paid it from June 1998 to 2000 and again from December 2003 to February 2005. In 2005, a high-level committee recommended recovery of excess payments, leading Gujarat Urja to file a petition before the Gujarat Electricity Regulatory Commission (GERC) under Section 86(1)(f) of the Electricity Act, 2003, seeking recovery of deemed generation incentive paid from 1997-98 to 2005-06. CLP resisted, arguing estoppel and that the matter had been closed by a supplementary agreement dated 05.12.2003. The GERC held that the 1995 notification applied and that deemed generation incentive was not payable, but limited recovery to three years prior to the petition (i.e., from 14.09.2002), deeming earlier claims time-barred. CLP also claimed interest on a deemed loan component of ₹53.9 crores, which the supplementary agreement recognized as own capital with 14% interest from 01.07.2003 to 31.03.2009. CLP sought interest for the period prior to 2003, but GERC and APTEL rejected this, holding that the supplementary agreement was a complete bargain and no interest was payable for the past. The Supreme Court upheld APTEL's decision, finding that the 1995 notification applied to the PPA and that the supplementary agreement precluded any retrospective claim for interest. The Court also upheld the limitation period applied by GERC. Both appeals were dismissed.

Headnote

A) Electricity Law - Tariff Determination - Deemed Generation Incentive - Section 43A, Electricity Supply Act, 1948 - Notification dated 06.11.1995 capped deemed generation incentive for naphtha-based plants - Held that the notification applied to the PPA and CLP was not entitled to incentive beyond the cap; recovery of excess payments was limited to three years prior to filing of petition (Paras 2-5).

B) Contract Law - Supplementary Agreement - Final Settlement - Clause 7.5.14(a) of Supplementary Agreement dated 05.12.2003 recognized ₹53.9 crores as own capital with 14% interest from 01.07.2003 to 31.03.2009 - Held that this clause constituted a complete bargain and no interest was payable for prior period; claim for retrospective interest was barred (Paras 7-13).

C) Limitation - Recovery of Excess Payments - Section 86(1)(f), Electricity Act, 2003 - GERC allowed recovery only for three years prior to filing of petition - Held that recovery for period prior to 14.09.2002 was time-barred (Para 5).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the generating company is entitled to deemed generation incentive despite the 1995 notification capping it; whether the supplementary agreement precludes recovery of excess incentive paid; whether interest on deemed loan component is payable for period prior to supplementary agreement.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Supreme Court dismissed both appeals, upholding the APTEL order. It held that the notification dated 06.11.1995 applied to the PPA and that deemed generation incentive was not payable. Recovery of excess payments was limited to three years prior to filing of petition. The supplementary agreement was a complete bargain and no interest on deemed loan was payable for the period prior to 01.07.2003.

Law Points

  • Electricity Act
  • 2003
  • Section 125
  • Electricity Supply Act
  • 1948
  • Section 43A
  • Power Purchase Agreement
  • Deemed Generation Incentive
  • Estoppel
  • Limitation
  • Supplementary Agreement
  • Interest on Loan Capital
  • Bullet Repayment
Subscribe to unlock Law Points Subscribe Now

Case Details

2020 LawText (SC) (5) 8

Civil Appeal No. 2793 of 2010 and Civil Appeal No. 2969 of 2010

2020-05-06

S. Ravindra Bhat

CLP India Pvt. Ltd. (in CA 2793/2010) and Gujarat Urja Vikas Nigam Ltd. (in CA 2969/2010)

Gujarat Urja Vikas Nigam Ltd. & Anr. (in CA 2793/2010) and CLP India Pvt. Ltd. (in CA 2969/2010)

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Appeals under Section 125 of the Electricity Act, 2003 against order of Appellate Tribunal for Electricity (APTEL) regarding recovery of deemed generation incentive and interest on deemed loan.

Remedy Sought

CLP sought to avoid recovery of deemed generation incentive and claimed interest on deemed loan component; Gujarat Urja sought recovery of excess incentive paid.

Filing Reason

Dispute over applicability of 1995 notification capping deemed generation incentive and interpretation of supplementary agreement regarding interest on deemed loan.

Previous Decisions

GERC held that deemed generation incentive was not payable but limited recovery to three years; APTEL upheld GERC's order.

Issues

Whether the notification dated 06.11.1995 capping deemed generation incentive applied to the PPA between CLP and Gujarat Urja. Whether the supplementary agreement dated 05.12.2003 precluded recovery of excess incentive paid prior to its execution. Whether CLP was entitled to interest on the deemed loan component for the period prior to 01.07.2003. Whether the claim for recovery of excess incentive was barred by limitation for the period prior to 14.09.2002.

Submissions/Arguments

CLP argued that the 1995 notification did not apply to the PPA and that principles of estoppel precluded recovery; also claimed interest on deemed loan for past period. Gujarat Urja argued that the 1995 notification applied and that the supplementary agreement did not waive recovery of excess incentive; also contended that interest on deemed loan was not payable for past period.

Ratio Decidendi

The notification dated 06.11.1995, being a statutory notification under Section 43A of the Electricity Supply Act, 1948, applied to the PPA and capped deemed generation incentive. The supplementary agreement dated 05.12.2003 constituted a complete settlement of all outstanding issues, including the treatment of ₹53.9 crores as own capital with interest only from 01.07.2003 to 31.03.2009, barring any retrospective claim. Recovery of excess payments was subject to limitation of three years under the Electricity Act, 2003.

Judgment Excerpts

The GERC, by its order held that Note 2 (introduced by the notification of 06.11.1995) was applicable to the project and thus deemed generation incentive is not payable to CLP. The APTEL concurred with the decision of the GERC and held that clause 7.5.14(a) of the supplementary agreement did not oblige Gujarat Urja to refund interest paid upon the deemed loan component upon the equity portion treated as deemed loan, i.e. ₹ 53.9 crores for any period prior to 01.07.2003.

Procedural History

Gujarat Urja filed Petition No.874/2006 before GERC under Section 86(1)(f) of the Electricity Act, 2003 for recovery of deemed generation incentive. GERC allowed recovery for three years prior to filing. CLP appealed to APTEL (Appeal No.44/2009) regarding interest on deemed loan; APTEL dismissed the appeal. Both parties appealed to the Supreme Court under Section 125 of the Electricity Act, 2003.

Acts & Sections

  • Electricity Act, 2003: Section 86(1)(f), Section 125
  • Electricity Supply Act, 1948: Section 43A
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Dismisses Appeals of Generating Company and State Utility in Electricity Tariff Dispute. Deemed Generation Incentive Not Payable After 1995 Notification; Supplementary Agreement Bars Retrospective Interest on Deemed Loan.
Related Judgement
Supreme Court Supreme Court Partially Allows Landowners in Land Acquisition Appeal by Modifying Deduction for Terrorism Shadow. High Court's Additional 25% Cut for Terrorism Shadow Set Aside as Market Value Already Reflects Depressed Prices Under Section 4 of Land...