Case Note & Summary
The Supreme Court allowed the appeal filed by South East Asia Marine Engineering and Constructions Ltd. (SEAMEC Ltd.) against the judgment of the Gauhati High Court, which had set aside an arbitral award in favor of the appellant. The dispute arose from a contract awarded by Oil India Limited to the appellant for well drilling operations in Assam. During the contract period, the price of High Speed Diesel (HSD), an essential input, increased. The appellant claimed reimbursement under Clause 23 of the contract, which provided for adjustment in case of 'subsequently enacted law' affecting costs. The respondent rejected the claim, leading to arbitration. The Arbitral Tribunal, by majority, held that an increase in HSD price through a circular issued under State or Union authority had the 'force of law' and fell within Clause 23, awarding Rs. 98,89,564.33 with interest. The respondent challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996 before the District Judge, who upheld the award. On appeal under Section 37, the High Court set aside the award, holding that the Tribunal's interpretation was erroneous and against public policy. The Supreme Court examined the scope of judicial review under Section 34, emphasizing that courts can interfere only on limited grounds, such as fraud, corruption, or violation of public policy. The Court noted that the Tribunal's interpretation of Clause 23 was plausible and supported by reasoning, and that the High Court had erred by substituting its own view. The Court held that the award was not perverse or patently illegal, and therefore, the High Court's interference was unwarranted. The Supreme Court set aside the High Court's judgment and restored the arbitral award.
Headnote
A) Arbitration Law - Judicial Review of Arbitral Award - Section 34 of Arbitration and Conciliation Act, 1996 - Scope of interference - Court can set aside award only on grounds provided in Section 34; perversity must go to root of matter; alternative interpretation not sufficient - Held that High Court exceeded its jurisdiction by substituting its own view (Paras 11-13). B) Arbitration Law - Interpretation of Contract by Arbitral Tribunal - Section 28 of Arbitration and Conciliation Act, 1996 - Reasonable and fair interpretation - If two views are possible, court must defer to arbitrator's plausible view - Held that Arbitral Tribunal's interpretation of Clause 23 as including executive orders having force of law was reasonable and not perverse (Paras 15-17). C) Contract Law - Change in Law Clause - Clause 23 of Contract - Meaning of 'law' - Executive orders having force of law fall within ambit - Increase in HSD price through circular under State/Union authority triggers clause - Held that Arbitral Tribunal's view was plausible (Paras 3-4, 16).
Issue of Consideration
Whether the High Court was justified in setting aside the arbitral award under Section 37 of the Arbitration and Conciliation Act, 1996 on the ground that the Arbitral Tribunal's interpretation of Clause 23 of the contract was erroneous and against public policy.
Final Decision
The Supreme Court allowed the appeal, set aside the impugned judgment of the Gauhati High Court, and restored the arbitral award dated 19.12.2003 as modified on 11.03.2005.
Law Points
- Scope of judicial review under Section 34 of Arbitration and Conciliation Act
- 1996 is limited to grounds specified therein
- Court cannot interfere with arbitral award merely because alternative view exists
- Interpretation of contract by Arbitral Tribunal
- if reasonably possible
- must be upheld
- 'Change in law' clause includes executive orders having force of law.



