Supreme Court Allows Appeals of Housing Board Against High Court Order Directing Arbitration Tribunal to Entertain Fresh Claim Despite Prior Arbitral Award. Principle of Issue Estoppel and Finality of Award Under Arbitration Act, 1996 Applied.

  • 7
Judgement Image
Font size:
Print

Case Note & Summary

The case involves three civil appeals by the Madhya Pradesh Housing and Infrastructure Development Board against a common judgment of the Madhya Pradesh High Court. The dispute arose from a works contract for construction of houses at Bhopal, awarded to the respondent contractor K.P. Dwivedi in 2005. The contractor failed to complete the work within 18 months despite extensions, leading to rescission of the contract in June 2008. The contractor filed a writ petition in the High Court, which was disposed of by consent on 20 August 2008, referring the dispute to the Housing Commissioner as arbitrator. The contractor participated in the arbitration and filed a claim. The arbitrator passed an award on 7 November 2008 rejecting the contractor's claim and granting some relief to the Board. The contractor did not challenge the award under Section 34 of the Arbitration and Conciliation Act, 1996. Instead, he filed a fresh reference petition before the Madhya Pradesh Arbitration Tribunal under Section 7 of the Madhya Pradesh Madhyastham Adhikaran Adhiniyam, 1983, for the same claim. The Board raised preliminary objections that the dispute had already been adjudicated and the award had attained finality. The Tribunal dismissed the reference as not maintainable on 27 February 2017. The contractor then filed a review petition before the High Court seeking clarification of the 2008 consent order, which was dismissed. He then filed arbitration revisions under Section 19 of the 1983 Act challenging the Tribunal's order. The High Court allowed the revisions, quashing the Tribunal's order and directing it to decide the reference on merits. The Supreme Court allowed the Board's appeals, holding that the High Court erred. The Court noted that the contractor had consented to the arbitration before the Housing Commissioner, participated fully, and did not challenge the award. The award had become final. The fresh claim before the Tribunal was barred by issue estoppel and the principle of finality of judgments. The consent order of 2008 was binding and could not be collaterally attacked after nine years. The Court set aside the High Court's order and restored the Tribunal's order dismissing the reference.

Headnote

A) Arbitration Law - Issue Estoppel - Finality of Award - Section 34 Arbitration and Conciliation Act, 1996 - Section 7 M.P. Madhyastham Adhikaran Adhiniyam, 1983 - The respondent contractor, after participating in arbitration proceedings before the Housing Commissioner appointed by the High Court and receiving an adverse award, filed a fresh claim before the M.P. Arbitration Tribunal for the same dispute. The Supreme Court held that the award had attained finality as it was not challenged under Section 34 of the Arbitration Act, 1996, and the fresh claim was barred by issue estoppel. The High Court's order directing the Tribunal to entertain the claim was set aside. (Paras 1-12)

B) Arbitration Law - Consent Order - Binding Effect - The order of the High Court referring the dispute to the Housing Commissioner was a consent order, and even if erroneous, it binds the parties until set aside by a competent court. The respondent could not collaterally attack the order after nine years. (Paras 6-10)

C) Arbitration Law - Jurisdiction - Waiver of Objection - In Madhya Pradesh Rural Road Development Authority vs. L.G. Chaudhary Engineers and Contractors, (2018) 10 SCC 826, it was held that if no objection to jurisdiction was taken at the relevant stage, the award cannot be annulled on that ground. The respondent had not raised any objection to the arbitrator's jurisdiction. (Para 11)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether a fresh claim petition before the M.P. Arbitration Tribunal under the 1983 Act is maintainable when the same dispute had already been adjudicated by an arbitrator appointed by the High Court and an award had been passed which attained finality.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Supreme Court allowed the appeals, set aside the impugned judgment and order of the High Court dated 08.05.2018, and restored the order of the M.P. Arbitration Tribunal dated 27.02.2017 dismissing the reference as not maintainable.

Law Points

  • Issue Estoppel
  • Finality of Arbitral Award
  • Jurisdiction of Arbitration Tribunal
  • Consent Order Binding Effect
  • Section 34 Arbitration Act 1996
  • Section 7 M.P. Madhyastham Adhikaran Adhiniyam 1983
Subscribe to unlock Law Points Subscribe Now

Case Details

2021 LawText (SC) (12) 110

Civil Appeal No. 6768 of 2021 (with connected appeals)

2021-10-26

M. R. Shah

Shri Bharat Singh (for appellants), Shri Kavin Gulati (for respondent)

M.P. Housing and Infrastructure Development Board & Anr.

K.P. Dwivedi

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Civil appeals against High Court order in arbitration revision petitions.

Remedy Sought

Appellants sought to set aside the High Court order directing the M.P. Arbitration Tribunal to entertain the respondent's fresh claim reference.

Filing Reason

The respondent contractor filed a fresh claim before the M.P. Arbitration Tribunal after an earlier arbitral award had been passed and had become final.

Previous Decisions

The M.P. Arbitration Tribunal dismissed the reference as not maintainable on 27.02.2017. The High Court in revision quashed that order and directed the Tribunal to decide the reference on merits.

Issues

Whether the fresh claim petition before the M.P. Arbitration Tribunal under the 1983 Act is maintainable when the same dispute had already been adjudicated by an arbitrator appointed by the High Court and an award had been passed which attained finality. Whether the principle of issue estoppel applies to bar the fresh claim.

Submissions/Arguments

Appellants argued that the earlier award had attained finality as it was not challenged under Section 34 of the Arbitration Act, 1996, and the fresh claim was barred by issue estoppel. The consent order referring the dispute to the Housing Commissioner was binding. Respondent argued that the 1983 Act governed works contracts and the Tribunal had exclusive jurisdiction, and the earlier arbitration was without jurisdiction.

Ratio Decidendi

The principle of issue estoppel applies to arbitration proceedings. Once an arbitral award has been passed and has attained finality (not challenged under Section 34 of the Arbitration Act, 1996), a fresh claim for the same dispute before another forum is not maintainable. A consent order referring the dispute to arbitration is binding on the parties and cannot be collaterally attacked after a long delay.

Judgment Excerpts

The learned Arbitrator passed an award on 07.11.2008 rejecting the claim of the respondent contractor and granting some relief in favour of the appellants. Instead of challenging the said award by way of an application under Section 34 of the Arbitration and Conciliation Act, 1996, the respondent filed a fresh Reference Petition before the Madhya Pradesh Arbitration Tribunal under Section 7 of the Madhya Pradesh Madhyastham Adhikaran, Vindhyachal, Bhopal. The order passed by the High Court referring the dispute between the parties to the Arbitrator Housing Commissioner was a consent order and the same was as per the relevant arbitration clause in the agreement entered into between the parties. In the case of Madhya Pradesh Rural Road Development Authority and Another vs. L.G. Chaudhary Engineers and Contracters, (2018) 10 SCC 826, relating to the issue of jurisdiction of the M.P. Tribunal, this Hon’ble Court has categorically held that if no objection to the jurisdiction of the arbitration was taken at the relevant stage, that award cannot be annulled only on that ground.

Procedural History

The respondent contractor filed a writ petition in the High Court which was disposed of by consent on 20.08.2008 referring the dispute to the Housing Commissioner as arbitrator. The arbitrator passed an award on 07.11.2008. The contractor did not challenge the award under Section 34 of the Arbitration Act, 1996. Instead, he filed a fresh reference before the M.P. Arbitration Tribunal under the 1983 Act. The Tribunal dismissed the reference on 27.02.2017. The contractor filed a review petition before the High Court seeking clarification of the 2008 order, which was dismissed on 07.09.2017. He then filed arbitration revisions under Section 19 of the 1983 Act, which were allowed by the High Court on 08.05.2018, quashing the Tribunal's order. The Board appealed to the Supreme Court.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 34
  • Madhya Pradesh Madhyastham Adhikaran Adhiniyam, 1983: Section 7, Section 19
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Allows Appeal in Recovery Suit — Holds That High Court Erred in Dismissing Suit on Grounds Not Raised in Pleadings and Without Considering Documentary Evidence. The Court restored the decree for recovery of Rs.96,41,765.31 with intere...
Related Judgement
Supreme Court Supreme Court Allows Appeals of Housing Board Against High Court Order Directing Arbitration Tribunal to Entertain Fresh Claim Despite Prior Arbitral Award. Principle of Issue Estoppel and Finality of Award Under Arbitration Act, 1996 Applied.