Supreme Court Allows Appeals in Part, Holds Interest on Delayed Payments Act, 1993 Applicable to Contracts Entered Before Its Commencement for Delays Occurring After 23.09.1992. The Court ruled that the Act is retroactive and applies to all payments made after its commencement, and that a suit for interest alone is maintainable.

  • 4
Judgement Image
Font size:
Print

Case Note & Summary

The Supreme Court considered appeals arising from a common judgment of the Gauhati High Court which had set aside trial court decrees in favor of suppliers (appellants) claiming interest on delayed payments under the Interest on Delayed Payment to Small Scale and Ancillary Industrial Undertakings Act, 1993. The appellants, including M/s Shanti Conductors (P) Ltd., M/s Trusses and Towers (P) Ltd., and M/s Brahmaputra Concrete Pipe Industries, had supplied goods to the Assam State Electricity Board under contracts entered into before the Act came into force on 23.09.1992. Payments were made after that date, and the suppliers filed suits for interest on delayed payments. The trial courts decreed the suits, but the High Court, relying on this Court's judgment in Purbanchal Cables & Conductors Pvt. Ltd. v. Assam State Electricity Board, (2012) 7 SCC 462, held that the Act does not apply to contracts entered into prior to its commencement. The suppliers appealed. The key legal issues were whether the Act applies retroactively to contracts entered before 23.09.1992 for delays occurring after that date, whether a suit for interest alone is maintainable, whether the Purbanchal Cables judgment operates as res judicata, and whether the suits were barred by limitation. The Court analyzed Sections 3, 4, and 5 of the Act, noting that the Act was enacted to provide a boost to small-scale industries and that the right to interest accrues on the date of payment, not the date of contract. It held that the Act is retroactive, applying to all payments made after its commencement, regardless of when the contract was entered. The Court also held that a suit for interest alone is maintainable, as the right to interest is a separate cause of action. Regarding res judicata, the Court found that the Purbanchal Cables judgment did not consider the issue of retroactivity and thus was sub silentio on that point. On limitation, the Court held that the suits were filed within three years from the date of payment, as per Article 113 of the Limitation Act, 1963. The Court allowed the appeals in part, setting aside the High Court's judgments and restoring the trial court decrees, but with modifications to the rate of interest as per the Act. The Court directed that interest be calculated at the rate specified in the Act from the due date until payment, and that the Board pay the amounts within three months.

Headnote

A) Interest on Delayed Payments - Retroactive Application - Interest on Delayed Payment to Small Scale and Ancillary Industrial Undertakings Act, 1993, Sections 3, 4, 5 - The Act applies to contracts entered into prior to 23.09.1992 for delays occurring after that date, as the right to interest accrues on the date of payment, not the date of contract - Held that the Act is retroactive, not retrospective, and applies to all payments made after its commencement (Paras 44-50).

B) Interest on Delayed Payments - Maintainability of Suit for Interest Alone - Interest on Delayed Payment to Small Scale and Ancillary Industrial Undertakings Act, 1993, Sections 3, 4, 5 - A suit for recovery of interest alone under the Act is maintainable, as the right to interest is a separate cause of action - Held that the supplier can sue for interest even after accepting the principal amount without protest (Paras 51-55).

C) Res Judicata - Applicability of Purbanchal Cables Judgment - Interest on Delayed Payment to Small Scale and Ancillary Industrial Undertakings Act, 1993 - The judgment in Purbanchal Cables & Conductors Pvt. Ltd. v. Assam State Electricity Board, (2012) 7 SCC 462, which held that the Act has no retrospective application, does not operate as res judicata in the present case as the issue of retroactive application was not considered - Held that the earlier decision was sub silentio on the point of retroactivity (Paras 56-60).

D) Limitation - Suit for Interest Under the Act - Interest on Delayed Payment to Small Scale and Ancillary Industrial Undertakings Act, 1993, Sections 3, 4, 5 - The suit for interest is not barred by limitation as the cause of action arises on the date of payment, and the suit was filed within three years from that date - Held that the limitation period under Article 113 of the Limitation Act, 1963 applies (Paras 61-65).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the Interest on Delayed Payments to Small Scale and Ancillary Industrial Undertakings Act, 1993 applies to contracts entered into prior to its commencement (23.09.1992) for delays occurring after that date; whether a suit for recovery of interest alone under the Act is maintainable; whether the judgment in Purbanchal Cables operates as res judicata; whether the suit is barred by limitation.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Supreme Court allowed the appeals in part, setting aside the High Court's judgments and restoring the trial court decrees, but with modifications to the rate of interest as per the Act. The Court directed that interest be calculated at the rate specified in the Act from the due date until payment, and that the Board pay the amounts within three months.

Law Points

  • Interest on Delayed Payment to Small Scale and Ancillary Industrial Undertakings Act
  • 1993
  • Retroactive application
  • Maintainability of suit for interest alone
  • Res judicata
  • Limitation
Subscribe to unlock Law Points Subscribe Now

Case Details

2019 LawText (SC) (1) 6

Civil Appeal Nos.8442-8443 of 2016, Civil Appeal No.8445 of 2016, Civil Appeal No.8448 of 2016, Civil Appeal No.8450 of 2016

2019-01-23

Ashok Bhushan, J.

Shri Ajit Kumar Sinha, Shri Basava Prabhu S. Patil, Shri Navaniti Prasad Singh, Shri Vijay Hansaris

M/S. Shanti Conductors(P) Ltd. & Anr.; M/S. Trusses and Towers (P)Ltd.; Assam State Electricity Board & Anr.; M/S. Brahmaputra Concrete Pipe Industries

Assam State Electricity Board & Ors.; Assam State Electricity Board & Anr.; M/S. Trusses and Towers (P) Ltd.; Assam State Electricity Board

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Civil appeals against judgment of Gauhati High Court setting aside trial court decrees in suits for recovery of interest on delayed payments under the Interest on Delayed Payment to Small Scale and Ancillary Industrial Undertakings Act, 1993.

Remedy Sought

Appellants (suppliers) sought recovery of interest on delayed payments from the Assam State Electricity Board under the Act.

Filing Reason

The Board delayed payments for supplies made under contracts entered into before the Act came into force, and the suppliers claimed interest under the Act.

Previous Decisions

Trial court decreed the suits; High Court in first appeal set aside the decrees relying on Purbanchal Cables judgment; Full Bench of High Court had earlier held the Act applicable; this Court in Purbanchal Cables held the Act not retrospective.

Issues

Whether the Interest on Delayed Payments to Small Scale and Ancillary Industrial Undertakings Act, 1993 applies to contracts entered into prior to its commencement (23.09.1992) for delays occurring after that date? Whether a suit for recovery of interest alone under the Act is maintainable? Whether the judgment in Purbanchal Cables operates as res judicata? Whether the suit is barred by limitation?

Submissions/Arguments

Appellants argued that the Act is retroactive and applies to all payments made after its commencement, and that a suit for interest alone is maintainable. Respondent Board argued that the Act does not apply to contracts entered before its commencement, and that the Purbanchal Cables judgment is binding.

Ratio Decidendi

The Interest on Delayed Payment to Small Scale and Ancillary Industrial Undertakings Act, 1993 is retroactive in nature, applying to all payments made after its commencement (23.09.1992) regardless of when the contract was entered. A suit for recovery of interest alone under the Act is maintainable. The Purbanchal Cables judgment does not operate as res judicata as it did not consider the issue of retroactivity. The suit is not barred by limitation as the cause of action arises on the date of payment.

Judgment Excerpts

The Act was enacted in order to provide a boost to the small scale and ancillary industries. The right to interest accrues on the date of payment, not the date of contract. The Act is retroactive, not retrospective, and applies to all payments made after its commencement.

Procedural History

Suppliers filed suits for interest on delayed payments in trial court, which decreed the suits. Board appealed to Gauhati High Court, which referred questions to Full Bench. Full Bench answered in favor of suppliers. Board appealed to Supreme Court, which in Purbanchal Cables held Act not retrospective. High Court then set aside trial court decrees. Suppliers appealed to Supreme Court.

Acts & Sections

  • Interest on Delayed Payment to Small Scale and Ancillary Industrial Undertakings Act, 1993: 3, 4, 5
  • Limitation Act, 1963: Article 113
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Dismisses Appeals by Private Company and Directors in Coal Scam Case, Upholds CBI Investigation. Post-Facto Consent Under Section 6 of DSPE Act Valid for Public Servants Not Named in FIR, Private Individuals Lack Locus to Challenge Inve...
Related Judgement
Supreme Court Supreme Court Allows Appeals in Part, Holds Interest on Delayed Payments Act, 1993 Applicable to Contracts Entered Before Its Commencement for Delays Occurring After 23.09.1992. The Court ruled that the Act is retroactive and applies to all payments ...