Supreme Court Upholds Rejection of Tender for Non-Compliant Bank Guarantee in Public Works Contract. Material Deviation in Performance Security Period Cannot Be Condoned After Bid Submission.

  • 4
Judgement Image
Font size:
Print

Case Note & Summary

The case arose from a tender called by the Vidarbha Irrigation Development Corporation for balance earthwork in a canal. Three bidders responded: Respondent No. 1 (Rs. 39.53 crores), Respondent No. 2 (Rs. 39.15 crores, the lowest), and Respondent No. 3 (Rs. 46.81 crores). The tender conditions required a performance security bank guarantee valid for 40 months. Respondent No. 2 initially submitted a bank guarantee valid for only 6 months. One day after bid opening, Respondent No. 2 sought to extend the validity to 40 months. The Tender Evaluation Committee accepted the bid on 07.07.2018. Respondent No. 1 challenged this acceptance before the High Court, which set aside the acceptance. The appellant and Respondent No. 2 appealed to the Supreme Court. The Supreme Court examined the tender conditions, particularly Clauses 2.15 and 2.22, and the pre-tender conference where it was clarified that the bank guarantee period could not be modified. The court held that the initial submission of a 6-month bank guarantee was a material deviation that could not be condoned after bid submission. The court emphasized that the tender conditions were clear and that allowing post-bid corrections would undermine the competitive bidding process and give an unfair advantage to the bidder. The court also noted that the difference in bids (Rs. 37 lakhs) did not justify compromising the integrity of the tender process. The Supreme Court dismissed the appeals, upholding the High Court's decision to reject the bid of Respondent No. 2.

Headnote

A) Tender Law - Material Deviation - Performance Security - Bank Guarantee Period - Clause 2.22 of Tender Conditions - The bidder furnished a bank guarantee valid for 6 months instead of the required 40 months. The pre-tender conference clarified that modification of this clause was not permissible. The court held that this was a material deviation that could not be condoned after bid submission, as it affected the employer's rights and the competitive position of other bidders. (Paras 6-10)

B) Tender Law - Conditional Tenders - Rejection - Clause 2.15 of Tender Conditions - The tender conditions explicitly stated that conditional tenders or those deviating from terms would be rejected as non-responsive. The court held that the bid with an insufficient bank guarantee period was a conditional tender and liable to rejection. (Paras 6-7)

C) Judicial Review - Administrative Decisions - Tender Matters - The court reiterated that judicial review in tender matters is limited to examining whether the decision-making process is arbitrary, irrational, or mala fide. However, where the authority acts contrary to the tender conditions, the court can interfere. (Para 11)

D) Public Interest - Competitive Bidding - Savings to Exchequer - While the difference in bids was about Rs. 37 lakhs, the court held that public interest in maintaining the integrity of the tender process and ensuring a level playing field outweighs the mere saving of money. (Para 11)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether a bidder's failure to furnish a bank guarantee for the required period (40 months) at the time of tender submission constitutes a material deviation that cannot be condoned subsequently, and whether the acceptance of such a bid by the tender evaluation committee is valid.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Supreme Court dismissed the appeals, upholding the High Court's judgment that the bid of Respondent No. 2 was non-responsive and liable to rejection.

Law Points

  • Tender law
  • Material deviation
  • Performance security
  • Bank guarantee period
  • Judicial review of administrative decisions
  • Public interest in competitive bidding
Subscribe to unlock Law Points Subscribe Now

Case Details

2019 LawText (SC) (1) 115

Civil Appeal No. 1049 of 2019 (Arising out of SLP (C) No. 26811 of 2018) with Civil Appeal No. 1050 of 2019 (Arising out of SLP (C) No. 27818 of 2018)

2019-01-22

Rohinton F. Nariman

Vidarbha Irrigation Development Corporation

M/S Anoj Kumar Garwala

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Civil appeal against High Court judgment setting aside acceptance of tender bid.

Remedy Sought

Appellant sought to set aside the High Court judgment and uphold the acceptance of Respondent No. 2's bid.

Filing Reason

The appellant challenged the High Court's decision that the bid of Respondent No. 2 was non-responsive due to insufficient bank guarantee period.

Previous Decisions

The High Court had set aside the acceptance of Respondent No. 2's bid.

Issues

Whether the initial submission of a bank guarantee for 6 months instead of 40 months is a material deviation. Whether such deviation can be condoned after bid opening. Whether the acceptance of the bid by the Tender Evaluation Committee was valid.

Submissions/Arguments

Appellant argued that the deficiency was made good after being pointed out, and the bid was accepted as the lowest, saving public money. Respondent No. 1 argued that the deviation was material and could not be condoned, as per tender conditions and pre-tender clarifications.

Ratio Decidendi

A bid that does not conform to a material tender condition, such as the period of a bank guarantee for performance security, cannot be condoned after bid submission. The tender conditions must be strictly adhered to, and any deviation that affects the employer's rights or the competitive position of other bidders is material and renders the bid non-responsive.

Judgment Excerpts

Clause 2.15, as set out hereinabove, makes it clear that it is only at a pre-tender stage that a clarification may be obtained regarding tender conditions. The bid of Respondent No. 2 was non-responsive and could not have been accepted. Public interest in maintaining the integrity of the tender process outweighs the mere saving of money.

Procedural History

The tender was called on 06.01.2018. Bids were opened on 06.04.2018. Respondent No. 2 submitted a bank guarantee valid for 6 months on 12.03.2018, and extended it on 07.04.2018. The Tender Evaluation Committee accepted the bid on 07.07.2018. Respondent No. 1 challenged this in the High Court, which set aside the acceptance. The appellant and Respondent No. 2 appealed to the Supreme Court.

Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Upholds Rejection of Tender for Non-Compliant Bank Guarantee in Public Works Contract. Material Deviation in Performance Security Period Cannot Be Condoned After Bid Submission.
Related Judgement
Supreme Court Supreme Court Allows Flat Purchasers' Appeal in Consumer Dispute Against Developer for Delayed Possession — Interest Extended Until Actual Possession. The court held that the NCDRC's limitation of interest to 31 July 2016 was unjustified as many pu...