Supreme Court Allows Carrying Cost in Change in Law Claims Under PPA — Restitutionary Principle Upheld. Article 13.2 of Power Purchase Agreement Entitles Generating Company to Carrying Cost from Date of Change in Law Till Approval.

  • 5
Judgement Image
Font size:
Print

Case Note & Summary

The case involves appeals by Uttar Haryana Bijli Vitran Nigam Ltd. and Dakshin Haryana Bijli Vitran Nigam Ltd. (Haryana Discoms) and Gujarat Urja Vikas Nigam Ltd. (GUVNL) against Adani Power Ltd. regarding the payment of carrying cost under Power Purchase Agreements (PPAs) due to change in law events. Adani Power Ltd., a generating company under the Electricity Act, 2003, operates a 4620 MW coal-fired power plant at Mundra, Gujarat, established in a Special Economic Zone (SEZ) approved by the Ministry of Commerce and Industry. The SEZ Act, 2005 provided exemptions from customs, excise, and service tax, which were withdrawn by notifications dated 06.04.2015 and 16.02.2016. Adani Power filed a petition before the Central Electricity Regulatory Commission (CERC) seeking compensation for change in law under Article 13 of the PPAs. The CERC allowed compensation for the added costs but denied carrying cost from the date of change in law till the date of approval, relying on its earlier order and distinguishing the Supreme Court judgment in National Thermal Power Corporation Ltd. v. Madhya Pradesh State Electricity Board. The Appellate Tribunal for Electricity reversed this decision, holding that Article 13.2 of the PPAs, which aims to restore the affected party to the same economic position as if the change in law had not occurred, implies entitlement to carrying cost on restitutionary principles. The Supreme Court, after hearing arguments, upheld the Appellate Tribunal's judgment. The Court examined the relevant provisions of the PPAs, particularly Article 13.2, which expressly provides for restoration to the same economic position. The Court noted that the PPA includes provisions for late payment surcharge and supplementary bills, but does not exclude carrying cost. The Court held that the restitutionary principle in Article 13.2, combined with the absence of any prohibition, entitles the respondent to carrying cost from the effective date of change in law till the date of approval. The appeals were dismissed, affirming the decision of the Appellate Tribunal.

Headnote

A) Electricity Law - Change in Law - Carrying Cost - Article 13 of Power Purchase Agreement - Restitutionary Principle - The issue was whether the generating company was entitled to carrying cost from the effective date of change in law till approval by the Commission. The Supreme Court held that Article 13.2 expressly provides for restoration to the same economic position as if change in law had not occurred, which includes carrying cost to compensate for the time gap. The Court upheld the Appellate Tribunal's decision allowing carrying cost, distinguishing the case from National Thermal Power Corporation Ltd. v. Madhya Pradesh State Electricity Board. (Paras 1-5)

B) Contract Law - Interpretation of Contracts - Express Provision for Restitution - Article 13.2 of PPA - The Court interpreted Article 13.2 of the PPA, which states that the purpose of compensating the affected party is to restore it to the same economic position as if the change in law had not occurred. This restitutionary principle, combined with the absence of any exclusion of carrying cost, led to the conclusion that carrying cost is payable from the date of change in law. (Paras 4-5)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the respondent is entitled to carrying cost from the date of change in law till the date of approval by the Commission under Article 13 of the PPAs.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Supreme Court dismissed the appeals, upholding the judgment of the Appellate Tribunal for Electricity that the respondent is entitled to carrying cost from the effective date of change in law till the date of approval by the Commission, based on the restitutionary principle in Article 13.2 of the PPAs.

Law Points

  • Change in Law
  • Carrying Cost
  • Restitution
  • Electricity Act 2003
  • PPA Interpretation
Subscribe to unlock Law Points Subscribe Now

Case Details

2019 LawText (SC) (2) 92

Civil Appeal No. 5865 of 2018 and Civil Appeal No. 6190 of 2018

2019-02-25

R.F. Nariman

Shri G. Umapathy, Shri V. Giri, Mr. Mukul Rohatgi

Uttar Haryana Bijli Vitran Nigam Ltd. [UHBVNL] & Anr. and Gujarat Urja Vikas Nigam Ltd.

Adani Power Ltd. & Ors.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Civil appeals against the judgment of the Appellate Tribunal for Electricity allowing carrying cost under change in law provisions of PPAs.

Remedy Sought

Appellants sought to set aside the Appellate Tribunal's order allowing carrying cost to the respondent.

Filing Reason

Dispute over entitlement to carrying cost from the date of change in law till approval by the Commission under Article 13 of the PPAs.

Previous Decisions

CERC allowed compensation for change in law but denied carrying cost; Appellate Tribunal reversed and allowed carrying cost.

Issues

Whether the respondent is entitled to carrying cost from the date of change in law till the date of approval by the Commission under Article 13 of the PPAs.

Submissions/Arguments

Appellants argued that carrying cost is not part of the PPAs and cannot be granted on equitable principles, relying on Supreme Court judgments. Respondent argued that Article 13.2 expressly provides a restitutionary principle, entitling them to carrying cost.

Ratio Decidendi

Article 13.2 of the PPA expressly provides for restoration to the same economic position as if change in law had not occurred, which includes carrying cost to compensate for the time gap between the change in law and its approval. The absence of an express provision for carrying cost does not preclude its grant when the restitutionary principle is embedded in the contract.

Judgment Excerpts

the purpose of compensating the Party affected by such Change in Law, is to restore through Monthly Tariff Payments, to the extent contemplated in this Article 13, the affected Party to the same economic position as if such Change in Law has not occurred. the principle of restitution and judgment of the Hon’ble Supreme Court in case of Indian Council for Enviro-Legal Action vs. Union of India & Ors., we are of the considered opinion that the Appellant is eligible for Carrying Cost

Procedural History

The respondent filed Petition No. 235/MP/2015 before CERC seeking compensation for change in law. CERC allowed compensation but denied carrying cost on 04.05.2017. The respondent appealed to the Appellate Tribunal for Electricity, which allowed carrying cost on 13.04.2018. The appellants then appealed to the Supreme Court.

Acts & Sections

  • Electricity Act, 2003: Section 2(18)
  • Special Economic Zones Act, 2005: Section 26
  • Customs Act, 1962:
  • Customs Tariff Act, 1975:
  • Central Excise Act, 1944:
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Allows Appeals Against High Court Order in Electricity Transmission Dispute — CERC's Power to Grant Compensation Upheld. The Court held that the CERC's regulatory functions under Section 79 of the Electricity Act, 2003 include the pow...
Related Judgement
Supreme Court Supreme Court Allows Carrying Cost in Change in Law Claims Under PPA — Restitutionary Principle Upheld. Article 13.2 of Power Purchase Agreement Entitles Generating Company to Carrying Cost from Date of Change in Law Till Approval.