Case Note & Summary
The case arises from arbitration proceedings under the Arbitration Act, 1940, concerning three agreements for irrigation works between the appellant contractor and the respondent State. The appellant had quoted rates 10-12% below standard and entered into agreements in 1979. Disputes arose, leading to arbitration. The arbitrator passed three awards on 19.8.1988, allowing various claims including extra lead (Claim 1), non-supply of food grains (Claim 3), short supply of cement (Claim 4), stock materials (Claim 7), and interest (Claim 9). The respondent filed applications under Sections 30 and 33 to set aside the awards, while the appellant sought decrees under Section 17. The sub-Court modified the award on Claim 1, set aside Claim 3, and upheld others. Both parties appealed to the High Court, which set aside the entire award, holding it contrary to Clause 59 of the agreement. The Supreme Court heard the appeal on the limited claims pressed by the appellant. The Court examined Clause 59, which barred claims for compensation due to departmental delays or hindrances, but held that it did not bar claims based on express contract terms or Section 70 of the Contract Act. On Claim 1 (extra lead), the Court found that the sub-Court erred in modifying the rate as there was no error apparent; the arbitrator's finding was based on evidence. On Claim 3 (food grains), the Court held that the arbitrator's finding that food grains were available but not supplied was a finding of fact, and the High Court erred in reappreciating evidence. On Claim 4 (cement), the Court upheld the arbitrator's reliance on Section 70 and adverse inference against the department. On Claim 7 (stock materials), the Court found the award justified. On Claim 9 (interest), the Court modified the rate to 9% per annum from the date of award till payment, while upholding the pre-award interest. The Supreme Court allowed the appeals in part, restoring the arbitrator's award on Claims 1, 3, 4, and 7, and modifying the interest rate.
Headnote
A) Arbitration Law - Jurisdiction of Arbitrator - Clause 59 of Agreement - Bar on Claims - The arbitrator's award was challenged on the ground that it violated Clause 59 of the contract, which prohibited claims for compensation due to departmental delays or hindrances. The Supreme Court held that Clause 59 did not bar claims based on express or implied terms of the contract or under Section 70 of the Contract Act, 1872, and that the arbitrator had jurisdiction to decide such claims. (Paras 1-6) B) Arbitration Law - Error Apparent on Face of Record - Modification of Award - The sub-Court modified the arbitrator's award on Claim No.1 (extra lead) by reducing the rate from Rs.15 per cubic meter to a rate calculated as per procedure, finding an error apparent. The Supreme Court held that the sub-Court exceeded its jurisdiction under Sections 30 and 33 of the Arbitration Act, 1940, as the arbitrator's finding on quantum was based on evidence and not perverse. (Paras 12-13) C) Contract Law - Section 70 of Contract Act, 1872 - Quantum Meruit - Claims for Extra Lead, Non-Supply of Food Grains, Short Supply of Cement, and Stock Materials - The arbitrator allowed these claims under Section 70, finding that the appellant had supplied materials and performed work not covered by the contract, and the respondent had accepted the benefit. The Supreme Court upheld the arbitrator's findings, holding that the claims were not barred by Clause 59 and that the arbitrator's decision was final on facts. (Paras 7-10) D) Arbitration Law - Interest on Arbitral Awards - Interest Act - The arbitrator awarded interest at 12% per annum from the date of claim petition. The Supreme Court modified the interest rate to 9% per annum from the date of the award till payment, in line with the prevailing rate, and held that interest for the pre-award period was within the arbitrator's discretion. (Para 11)
Issue of Consideration
Whether the High Court was justified in setting aside the arbitrator's award on the ground that it was contrary to Clause 59 of the Agreement, and whether the claims for extra lead, non-supply of food grains, short supply of cement, stock materials, and interest were sustainable under the contract and the Arbitration Act, 1940.
Final Decision
Appeals allowed in part. The Supreme Court set aside the High Court judgment and restored the arbitrator's award on Claims 1, 3, 4, and 7. On Claim 9 (interest), the Court modified the rate to 9% per annum from the date of the award till payment, instead of 12% per annum from the date of claim petition. The sub-Court's modification on Claim 1 was set aside. The matter was remanded for computation of amounts accordingly.
Law Points
- Arbitration Act
- 1940
- Sections 30
- 33
- 17
- Contract Act
- 1872
- Section 70
- Clause 59 of Agreement
- Interest Act
- Arbitrator's jurisdiction
- Error apparent on face of record
- Misconduct
- Modification of award
- Interest on arbitral claims.



