Supreme Court Upholds Distribution Licensee's Right to Levy Wheeling Charges on 110 kV Feeders — 110 kV HPCL Feeders Held Integral Part of Distribution Network Despite Voltage Level. The Court held that the functional use of the feeders for distribution to a single consumer, HPCL, determines their classification as distribution assets, not merely the voltage level under CEA Regulations, 2010.

  • 4
Judgement Image
Font size:
Print

Case Note & Summary

The case involves a dispute between Sai Wardha Power Generation Limited (SWPGL) and Hindustan Petroleum Corporation Limited (HPCL) on one side, and Tata Power Company Limited-Distribution (TPC-D) on the other, regarding the levy of wheeling charges for power supplied to HPCL through 110 kV feeders. HPCL had been receiving electricity from TPC since 1955, and in 2005, a power supply agreement was executed for additional 70 MW supply at 110 kV. In 2006, TPC trifurcated its assets into generation, transmission, and distribution entities. The 2x110 kV lines were capitalized in TPC-D's books in 2008, and HPCL paid wheeling charges since then. In 2014, TPC obtained a transmission licence that inadvertently included these lines. HPCL later sought open access to purchase power from SWPGL, and TPC-D levied wheeling charges. HPCL filed a petition before the Maharashtra Electricity Regulation Commission (MERC) seeking a declaration that TPC-D was not entitled to levy wheeling charges, arguing that the 110 kV lines were transmission assets. MERC allowed HPCL's petition, holding that the lines were part of the transmission system based on voltage classification under CEA Regulations, 2010, and directed refund of wheeling charges. The Appellate Tribunal for Electricity (APTEL) reversed MERC's order, holding that the 110 kV feeders were integral to TPC-D's distribution network and that TPC-D was entitled to levy wheeling charges. The Supreme Court upheld APTEL's decision, dismissing the appeals filed by SWPGL and HPCL. The Court held that the 110 kV feeders were always used for distribution to HPCL, a single consumer, and their inclusion in the transmission licence was an error. The Court emphasized that the functional use of the lines, not merely voltage level, determines whether they are distribution or transmission assets. The Court also noted that HPCL had paid wheeling charges for years without objection, and that the CEA Regulations' voltage classification is not absolute. The Court directed MERC to re-determine the wheeling charges at EHT level 110 kV, as HPCL had been paying higher charges. The judgment clarifies that a distribution licensee can own and operate lines at extra high voltage if they are used for distribution to consumers, and that a consumer cannot avoid wheeling charges by relying on voltage-based classification alone.

Headnote

A) Electricity Law - Wheeling Charges - Classification of 110 kV Feeders - Distribution vs Transmission - The core issue was whether 110 kV feeders from Trombay Generation Station to HPCL's premises are part of the distribution system or transmission system. The Supreme Court held that the 110 kV feeders are integral part of TPC-D's distribution network, and TPC-D is entitled to levy wheeling charges. The Court relied on the functional use of the feeders and the fact that they were always used for distribution to a single consumer, HPCL. (Paras 1-13)

B) Electricity Law - Open Access - Wheeling Charges - Consumer's Liability - HPCL, a consumer, sought to avoid wheeling charges by arguing that the 110 kV lines were transmission assets. The Court rejected this, holding that the consumer's connection to a distribution licensee's network, even at EHV level, does not convert the line into a transmission line. The Court emphasized that the classification depends on the function and not merely voltage level. (Paras 6-8)

C) Electricity Law - Regulatory Framework - CEA Regulations, 2010 - Voltage Classification - The CEA Regulations, 2010 classify voltage levels up to 33 kV as distribution and 66 kV and above as transmission. However, the Court held that this classification is not absolute and that a distribution licensee can own and operate lines at higher voltages if they are used for distribution to consumers. The Court distinguished the facts from the general voltage-based demarcation. (Paras 6-8)

D) Electricity Law - Licence - Erroneous Inclusion in Transmission Licence - Effect - TPC-T had inadvertently included the 110 kV feeders in its transmission licence. The Court held that this erroneous inclusion does not change the character of the feeders as distribution assets. The Commission had already rejected the amendment application, and the Tribunal had remanded it. The Court noted that the factual use and regulatory treatment of the feeders as distribution assets override the licence entry. (Paras 4-5)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether Tata Power Company Limited-Distribution (TPC-D) is entitled to levy wheeling charges for power supplied to HPCL through 110 kV feeders, and whether those feeders are part of the distribution system or transmission system.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Supreme Court dismissed the appeals, upholding the APTEL judgment. The Court held that the 110 kV feeders are integral part of TPC-D's distribution network, and TPC-D is entitled to levy wheeling charges. The Court directed MERC to re-determine the wheeling charges at EHT level 110 kV.

Law Points

  • Wheeling charges
  • Distribution network
  • Transmission network
  • Voltage classification
  • Open access
  • Electricity Act
  • 2003
  • CEA Regulations
  • 2010
Subscribe to unlock Law Points Subscribe Now

Case Details

2020 LawText (SC) (4) 40

Civil Appeal No.2228/2020 (@ Diary No.24669 of 2019) with Civil Appeal No.5049 of 2019

2020-04-03

L. Nageswara Rao, J.

Sai Wardha Power Generation Limited

The Tata Power Company Limited Distribution & Ors.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Civil appeals against the judgment of the Appellate Tribunal for Electricity (APTEL) regarding levy of wheeling charges on 110 kV feeders.

Remedy Sought

SWPGL and HPCL sought to set aside the APTEL order and restore the MERC order directing refund of wheeling charges.

Filing Reason

Dispute over whether TPC-D is entitled to levy wheeling charges for power supplied to HPCL through 110 kV feeders, which HPCL and SWPGL argued were transmission assets.

Previous Decisions

MERC allowed HPCL's petition, holding TPC-D not entitled to levy wheeling charges and directing refund. APTEL set aside MERC's order, holding TPC-D entitled to levy wheeling charges.

Issues

Whether the 110 kV HPCL feeders are part of the distribution system of TPC-D or qualify as transmission lines. Whether the erroneous inclusion of the 110 kV feeders in the transmission licence exempts HPCL from payment of wheeling charges.

Submissions/Arguments

HPCL and SWPGL argued that the 110 kV lines are transmission lines based on voltage classification under CEA Regulations, 2010, and their inclusion in the transmission licence. TPC-D argued that the feeders were always used for distribution to HPCL, were capitalized in its books, and HPCL had paid wheeling charges for years without objection.

Ratio Decidendi

The classification of a line as distribution or transmission depends on its functional use, not merely on voltage level. A distribution licensee can own and operate lines at extra high voltage if they are used for distribution to consumers. The erroneous inclusion of such lines in a transmission licence does not change their character as distribution assets.

Judgment Excerpts

The question that arises for our consideration in these Appeals is whether Tata Power Company Limited- Distribution is entitled to levy wheeling charges for the power supplied to Hindustan Petroleum Corporation Limited and wheeling charges for the power sourced from Sai Wardha Power Generation Limited through open access. The Appellate Tribunal framed two principal issues for consideration which are as follows: Issue No.1: Whether the 110 kV HPCL feeders are part of the Distribution system of TPC-D or can qualify as transmission lines in terms of the statutory framework and in the facts of the present case? Issue No.2: Whether the erroneous submission of TPC-T regarding 110 kV HPCL feeders in the transmission licence No.1 exempt HPCL from payment of wheeling charges?

Procedural History

HPCL filed a petition before MERC in 2017 seeking declaration that TPC-D cannot levy wheeling charges. MERC allowed the petition on 12.03.2018. TPC-D appealed to APTEL, which set aside MERC's order on 22.03.2018. SWPGL and HPCL filed appeals before the Supreme Court.

Acts & Sections

  • Electricity Act, 2003: Section 2(69), Section 2(72)
  • Central Electricity Authority (Technical Standards for Construction of Electrical Plants and Electric Lines) Regulations, 2010:
  • Indian Electricity Act, 1910:
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Upholds Distribution Licensee's Right to Levy Wheeling Charges on 110 kV Feeders — 110 kV HPCL Feeders Held Integral Part of Distribution Network Despite Voltage Level. The Court held that the functional use of the feeders for distrib...
Related Judgement
Supreme Court Supreme Court Dismisses Appeals Challenging Nomination of Daughter's Son as Sajjadah Nashin and Mutawalli. The Court upheld the concurrent findings that the word 'Khandan' in the Zabta includes the spiritual sect and not only male lineal descendants,...