Case Note & Summary
The case involves an appeal by the Lucknow Development Authority (LDA) against a Division Bench judgment of the Allahabad High Court (Lucknow Bench) dated January 15, 2014. The High Court had quashed LDA's order dated July 29, 2011 demanding development charges of Rs.1,57,22,056/- from the respondents (original landowners) upon restoration of their land under Section 17 of the Uttar Pradesh Urban Planning and Development Act, 1973. The High Court also imposed costs of Rs.1,00,000/- on LDA. The facts are that LDA acquired 168.592 hectares of land in 1981 for the Sitapur Road City Extension Scheme. The respondents' land measuring 1.200 hectares was part of this acquisition. In 2011, the State Government restored the land to the respondents under Section 17 of the Act, subject to payment of acquisition cost and development charges. The respondents challenged the demand before the High Court, which held that no development had been carried out on their specific land or its vicinity, and therefore development charges could not be levied. The Supreme Court allowed LDA's appeal, holding that the High Court's finding was erroneous. The Court noted that 97.1% of the total acquired land had been developed with roads, electricity, water, and sewer lines. Development must be assessed for the entire acquired land, not piecemeal. However, the Court found that the quantification of Rs.1,57,22,056/- was done without giving the respondents an opportunity of hearing, violating principles of natural justice. Therefore, the demand letter was set aside, and LDA was directed to re-determine the amount after providing a hearing. The Court also clarified that the respondents could seek remedies under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, if applicable.
Headnote
A) Land Acquisition - Restoration of Land - Development Charges - Section 17 of the Uttar Pradesh Urban Planning and Development Act, 1973 - The issue was whether development charges could be levied on restoration of land when the specific plot had not been developed. The Supreme Court held that development must be examined in respect of the entire acquired land, not just the particular plot. Since 97.1% of the acquired land was developed with roads, electricity, water, and sewer lines, the respondents were liable to pay development charges. (Paras 9-10) B) Natural Justice - Opportunity of Hearing - Quantification of Charges - The Court found that the demand of Rs.1,57,22,056/- was raised without giving any opportunity of hearing to the respondents. Therefore, the demand letter dated July 29, 2011 was set aside with liberty to the appellants to re-determine the amount after providing a hearing. (Para 11) C) Land Acquisition - Alternative Remedy - Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 - The Court observed that it would be open to the respondents to seek remedy under the 2013 Act in accordance with law. (Para 11)
Issue of Consideration
Whether the High Court was correct in setting aside the demand for development charges under Section 17 of the Uttar Pradesh Urban Planning and Development Act, 1973 on the ground that no development was carried out on the respondents' specific land.
Final Decision
The Supreme Court allowed the appeal, set aside the High Court's finding that development charges could not be claimed. However, the demand letter dated July 29, 2011 was set aside as it was issued without giving an opportunity of hearing to the respondents. The appellants were directed to re-determine the amount of acquisition cost and development charges in accordance with law after providing a hearing. The respondents were given liberty to seek remedy under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013.
Law Points
- Development charges under Section 17 of the Uttar Pradesh Urban Planning and Development Act
- 1973 are payable on restoration of land if development has been carried out on the acquired land as a whole
- not merely on the specific plot
- opportunity of hearing must be given before quantifying development charges.



