Bombay High Court Partially Allows Challenge to Arbitral Award in Pipeline Project Dispute — Interest Modified to Simple Interest. The court held that pre-reference interest was not permissible under the contract and compound interest was contrary to the agreement, modifying the award to simple interest at 18% per annum from the date of the award.

High Court: Bombay High Court Bench: BOMBAY
  • 47
Judgement Image
Font size:
Print

Case Note & Summary

The petitioner, Hindustan Petroleum Corporation Limited (HPCL), challenged an arbitral award dated 21 February 2012 under Section 34 of the Arbitration and Conciliation Act, 1996. The dispute arose from a contract for composite works (mechanical, electrical, and instrumentation) for terminals and stations at Awa, Ajmer, and Jaipur as part of the Mundra Delhi Pipeline Project. The respondent, Offshore Infrastructure Limited, was awarded the contract via a Fax of Acceptance dated 7 July 2006 at a total cost of Rs.19,95,30,359.78 with a completion period of 7 months. The project was delayed, and time extensions were granted. The respondent claimed amounts for work done, and the matter was referred to arbitration. The arbitral tribunal allowed claims 1 to 4 and awarded interest at 18% per annum compounded quarterly from various dates. HPCL challenged the award on the grounds that the interest awarded was contrary to the contract and public policy. The court held that the award of pre-reference interest was not permissible as the contract did not provide for interest prior to the reference. The court also held that the award of compound interest was contrary to the contract which provided for simple interest. The court modified the award to simple interest at 18% per annum from the date of the award till payment. The petition was partly allowed.

Headnote

A) Arbitration - Section 34 Challenge - Public Policy - Interest - The court examined whether the arbitral tribunal's award of interest at 18% per annum compounded quarterly was contrary to the contract and public policy. The court held that the award of pre-reference interest was not permissible as the contract did not provide for interest prior to the reference, and the award of compound interest was contrary to the contract which provided for simple interest. The court modified the award to simple interest at 18% per annum from the date of the award till payment. (Paras 1-16)

B) Arbitration - Interest - Section 31(7)(b) of the Arbitration and Conciliation Act, 1996 - The court interpreted Section 31(7)(b) which allows interest from the date of the award unless otherwise agreed. The court held that the tribunal's award of interest from the date of the award at 18% per annum compounded quarterly was not in accordance with the contract which provided for simple interest. The court reduced the interest to simple interest at 18% per annum from the date of the award. (Paras 10-16)

C) Arbitration - Unilateral Appointment of Arbitrator - Waiver - The court noted that the petitioner had not objected to the appointment of the arbitrator despite knowing the procedure, and thus waived the right to challenge the award on that ground. (Para 8)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the arbitral award granting pre-reference, pendente lite, and post-award interest at 18% per annum compounded quarterly is contrary to the contract and public policy under Section 34 of the Arbitration and Conciliation Act, 1996.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The petition is partly allowed. The arbitral award is modified to the extent that the respondent shall be entitled to simple interest at 18% per annum from the date of the award till payment. The award of pre-reference interest is set aside. The award of pendente lite interest is upheld but modified to simple interest.

Law Points

  • Section 34 of the Arbitration and Conciliation Act
  • 1996
  • Public policy
  • Interest under Section 31(7)(b) of the Arbitration Act
  • Pre-reference interest
  • Pendente lite interest
  • Post-award interest
  • Compound interest
  • Unilateral appointment of arbitrator
  • Waiver of right to object
Subscribe to unlock Law Points Subscribe Now

Case Details

2015 LawText (BOM) (07) 86

Arbitration Petition No.869 of 2012

2015-07-28

R.D. Dhanuka, J.

Mr. Minoo Siodia with Ms. Raksha Thakur and Mr. Siddharth Shenoy i/b Rustamji & Ginwala for the Petitioner; Mr. D. Singh i/b Mr. Sudheer Phadke for the Respondent

Hindustan Petroleum Corporation Limited

M/s. Offshore Infrastructure Limited

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Challenge to arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996

Remedy Sought

Petitioner sought to set aside the arbitral award dated 21 February 2012

Filing Reason

Petitioner challenged the award on the ground that the interest awarded at 18% per annum compounded quarterly was contrary to the contract and public policy

Previous Decisions

Arbitral tribunal allowed claims 1 to 4 and awarded interest at 18% per annum compounded quarterly

Issues

Whether the arbitral award granting pre-reference, pendente lite, and post-award interest at 18% per annum compounded quarterly is contrary to the contract and public policy under Section 34 of the Arbitration and Conciliation Act, 1996.

Submissions/Arguments

Petitioner argued that the award of interest at 18% per annum compounded quarterly was contrary to the contract which provided for simple interest and was against public policy. Respondent argued that the award was within the discretion of the tribunal and should not be interfered with.

Ratio Decidendi

The court held that pre-reference interest is not permissible unless provided in the contract. The contract provided for simple interest, so the award of compound interest was contrary to the contract and public policy. Under Section 31(7)(b) of the Arbitration Act, interest from the date of the award is at the rate specified in the award unless otherwise agreed, but the rate must be in accordance with the contract.

Judgment Excerpts

By this petition filed under section 34 of the Arbitration & Conciliation Act, 1996, the petitioner has impugned the arbitral award dated 21st February, 2012, thereby allowing claim nos.1 to 4 and interest thereon made by the respondent. The court held that the award of pre-reference interest was not permissible as the contract did not provide for interest prior to the reference. The court modified the award to simple interest at 18% per annum from the date of the award till payment.

Procedural History

The respondent filed claims before the arbitral tribunal. The tribunal passed an award on 21 February 2012 allowing claims 1 to 4 with interest at 18% per annum compounded quarterly. The petitioner filed this petition under Section 34 of the Arbitration Act on 28 July 2015.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: 34, 31(7)(b)
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Partially Allows Challenge to Arbitral Award in Pipeline Project Dispute — Interest Modified to Simple Interest. The court held that pre-reference interest was not permissible under the contract and compound interest was contrary ...
Related Judgement
High Court Bombay High Court Sanctions Scheme of Amalgamation of Twelve Transferor Companies with Pebble Bay Developers Private Limited under Sections 391-394 of the Companies Act, 1956. Court found compliance with statutory requirements and no objections from ...