Case Note & Summary
The dispute originated from a consultancy agreement dated 18 September 1995 between the Municipal Corporation of Greater Mumbai (MCGM) and Respondent for upgrading sewerage operations and maintenance services, a World Bank-funded project. The work was completed on 20 June 2001, but a payment dispute arose, leading the respondent to invoke arbitration on 9 August 2005. The MCGM appointed its nominee arbitrator on 7 October 2005. After discussions on conciliation, which did not materialize, the co-arbitrators appointed a presiding arbitrator on 24 April 2008, with the final appointment of Mr. Anwarul Haque on 12 November 2008. The MCGM challenged this appointment under Section 16 of the Arbitration and Conciliation Act, 1996, arguing it was a nullity as it occurred beyond 30 days from the second arbitrator's nomination, rendering the tribunal coram non judice. The arbitral tribunal dismissed this challenge on 17 July 2009, and a final award was passed on 5 June 2010. The MCGM filed an application under Section 34 to set aside the award, which was dismissed by the Single Judge of the Bombay High Court on 19-20 October 2022. An appeal under Section 37 was also dismissed by the Division Bench on 4 July 2025. The core legal issue was whether the tribunal was improperly constituted due to the late appointment of the presiding arbitrator, violating Clause 8.3(b) of the agreement. The appellant argued that the clause mandated appointment within 30 days, after which only the ICSID Secretary General could appoint, emphasizing party autonomy. The respondent likely defended the tribunal's interpretation. The Supreme Court analyzed the arbitration clause, noting that the 30-day period was directory, not mandatory, and the co-arbitrators retained power to appoint the presiding arbitrator. The Court found that interpreting the clause to strip the co-arbitrators of power after 30 days would lead to absurdity, as there was no time limit for ICSID reference. The tribunal's view was deemed the only reasonable interpretation, not warranting interference under Sections 34 or 37. Additionally, the Court held that the appellant's participation in proceedings constituted waiver under Section 4 and the challenge was barred by limitation. The decision affirmed the lower courts' rulings, dismissing the appeal and upholding the arbitral award.
Headnote
A) Arbitration Law - Arbitral Tribunal Constitution - Appointment of Presiding Arbitrator - Arbitration and Conciliation Act, 1996, Sections 16, 34, 37 - Dispute arose from a consultancy agreement for sewerage services; the appellant challenged the tribunal's jurisdiction under Section 16, arguing that the co-arbitrators' appointment of the presiding arbitrator after 30 days from the second arbitrator's nomination was invalid, making the tribunal coram non judice. The Supreme Court held that the 30-day period was directory, not mandatory, and the co-arbitrators retained power to appoint; the appellant's participation in proceedings constituted waiver under Section 4, and the challenge was barred by limitation. The award was upheld as the tribunal's interpretation of the arbitration clause was reasonable. (Paras 21-24, 26-27) B) Arbitration Law - Contractual Interpretation - Arbitration Agreement Clauses - Arbitration and Conciliation Act, 1996 - The appellant contended that Clause 8.3(b) of the agreement mandated appointment of the presiding arbitrator within 30 days, after which only the ICSID Secretary General could appoint, based on party autonomy. The Court found that interpreting the clause to render the co-arbitrators powerless after 30 days would lead to absurdity, as there was no time limit for ICSID reference; the tribunal's view that the provision was enabling and did not oust the co-arbitrators' power was the only reasonable interpretation, not warranting interference under Section 34 or 37. (Paras 22-24) C) Arbitration Law - Waiver and Limitation - Participation in Arbitral Proceedings - Arbitration and Conciliation Act, 1996, Section 4 - The appellant participated in preliminary meetings and raised jurisdictional objections only later. The Court held that this conduct amounted to waiver under Section 4, as the appellant continued with the arbitration without promptly challenging the appointment; additionally, the challenge was barred by limitation, as it was not raised in a timely manner after the appointment. This reinforced the validity of the tribunal's constitution. (Paras 22, 26)
Premium Content
The Headnote is only available to subscribed members.
Subscribe Now to access key legal points
Issue of Consideration: Whether the arbitral tribunal was improperly constituted due to the appointment of the Presiding Arbitrator beyond the 30-day period stipulated in the arbitration agreement, rendering the award a nullity.
Premium Content
The Issue of Consideration is only available to subscribed members.
Subscribe Now to access critical case issues
Final Decision
Supreme Court dismissed the appeal, upheld the arbitral award, and confirmed the judgments of the High Court and Arbitral Tribunal, finding no improper constitution of the tribunal.



