High Court Quashes Termination of Railway Contract as Arbitrary and Violative of Natural Justice. Writ Petition Maintainable Despite Arbitration Clause Under Article 226 of Constitution of India, as Termination Notices Dated 13.11.2025 and 02.12.2025 Were Issued Without Adequate Hearing and With Sufficient Time Remaining for Completion.

High Court: Bombay High Court Bench: AURANGABAD
  • 10
Judgement Image
Font size:
Print

Case Note & Summary

The dispute involved a registered partnership firm, Petitioner, challenging the termination of its contract with Central Railway authorities for construction work on the Ahmednagar–Beed–Parli Vaidyanath New Broad Gauge Line Project. The petitioner had entered into an agreement dated 17.08.2024, with the work value increased to approximately Rs.54.85 crores through supplemental agreements and the completion period extended to 31.03.2026. The respondent railway authorities issued a communication dated 13.11.2025 deciding to part terminate the contract, followed by a termination notice dated 02.12.2025, alleging delays and other issues. The petitioner filed a writ petition under Article 226 of the Constitution of India, contending that the termination was arbitrary, illegal, and violative of natural justice, and sought directions to complete the balance work and release payments. The core legal issues were the maintainability of the writ petition despite an arbitration clause in the contract and the validity of the termination actions. The petitioner argued that the writ petition was maintainable as the reliefs were declaratory and involved public law remedies, citing Union of India v. Tantia Construction Pvt. Ltd., and that the termination was unjustified as sufficient time remained for completion and the petitioner was not given a proper hearing. The respondents defended the termination as per contract terms and procedures. The court analyzed that the writ jurisdiction is not barred by an alternative remedy like arbitration, especially when natural justice is violated. It found the termination arbitrary because the petitioner had over 100 days left to complete the work, the allegations were trivial, and the petitioner was not afforded an adequate opportunity to be heard. The court quashed the termination notices, holding them illegal and violative of natural justice, and directed the respondents to allow the petitioner to complete the balance work within the extended period, subject to conditions, while preserving other remedies.

Headnote

A) Constitutional Law - Writ Jurisdiction - Maintainability Despite Arbitration Clause - Constitution of India, 1950, Article 226 - Petitioner challenged termination of railway contract under Article 226 despite arbitration clause in agreement - Court held writ petition maintainable as alternative remedy is not an absolute bar, relying on Supreme Court precedent in Union of India v. Tantia Construction Pvt. Ltd. - Held that violation of natural justice and arbitrariness in administrative action warrant exercise of writ jurisdiction (Paras 12, 17).

B) Contract Law - Termination of Contract - Arbitrariness and Natural Justice - Contract Act, 1872, General Principles - Railway authorities terminated contract via notices dated 13.11.2025 and 02.12.2025 - Court found termination arbitrary as petitioner had over 100 days remaining to complete work and allegations were trivial - Held that termination violated principles of natural justice as petitioner was not afforded adequate opportunity of hearing, making it illegal (Paras 10-11, 15-16).

C) Administrative Law - Natural Justice - Opportunity of Hearing - General Principles - Respondent issued termination notices without proper hearing to petitioner - Court reasoned that administrative actions must comply with natural justice, especially when affecting contractual rights - Held that failure to provide adequate opportunity rendered termination invalid (Paras 11, 16).

Issue of Consideration: Whether the writ petition under Article 226 of the Constitution of India is maintainable challenging the termination of a contract with an arbitration clause, and whether the termination notices dated 13.11.2025 and 02.12.2025 are arbitrary, illegal, and violative of natural justice

Final Decision

Court quashed termination notices dated 13.11.2025 and 02.12.2025 as illegal and violative of natural justice, directed respondents to allow petitioner to complete balance work within extended period up to 31.03.2026 subject to conditions, and preserved other remedies for parties

 

2026 LawText (BOM) (03) 154

Writ Petition No. 606 of 2026

2026-03-27

Smt. Vibha Kankanwadi J. , Hiten S. Venegavkar J.

2026:BHC-AUG:13099-DB

Mr. Prasadrao Vemulapalli, Advocate h/f Mr. A.A. Fulfagar,Advocate for Petitioner, Mr. N.S. Salunke, Advocate for Respondents No.1 to 3

M/s. MVV Satyanarayan A registered Partnership Firm, Through its Authorized Signatory, Mr. Niel S/o. Kakasaheb Patil

The General Manager, Central Railway, D.N. Road, Mumbai CSMT - 400001, The Chief Administrative Officer (Const.), Central Railway, New Administrative Building 6 th Floor, D.N. Road, Mumbai, CSMT – 400001, The Chief Engineer/C/Central CSMT Chief Administrative Officer (c)’s Office Central Railway, New Administrative Building 6 th Floor, D.N. Road, Mumbai, CSMT -400001

Nature of Litigation: Writ petition under Article 226 of the Constitution of India challenging termination of a contract

Remedy Sought

Petitioner seeks quashing of termination notices dated 13.11.2025 and 02.12.2025, direction to complete balance work, and release of payments

Filing Reason

Termination of contract alleged to be arbitrary, illegal, and violative of natural justice

Issues

Maintainability of writ petition under Article 226 despite arbitration clause in contract Validity of termination notices dated 13.11.2025 and 02.12.2025 as arbitrary and violative of natural justice

Submissions/Arguments

Petitioner argued termination was arbitrary as sufficient time remained for completion and allegations were trivial, and violative of natural justice due to lack of hearing Respondents argued termination was per contract terms and procedures Petitioner argued writ petition maintainable despite arbitration clause, citing Union of India v. Tantia Construction Pvt. Ltd.

Ratio Decidendi

Writ jurisdiction under Article 226 is maintainable despite an arbitration clause when administrative actions are arbitrary or violate natural justice; termination of contract must be based on valid grounds and comply with principles of natural justice, including adequate opportunity of hearing

Judgment Excerpts

The present Writ Petition is filed under Article 226 of the Constitution of India challenges the communication dated 13.11.2025 issued by Respondent No.3, whereby a decision was taken to part terminate the contract/agreement dated 17.08.2024 the impugned communications are bad in law writ petition is maintainable as alternative remedy is not an absolute bar

Procedural History

Writ petition filed under Article 226 of Constitution of India, rule made returnable forthwith, petition taken up for final disposal with consent of parties, reserved on 13 March 2026, pronounced on 27 March 2026

Related Judgement
High Court High Court Quashes Termination of Railway Contract as Arbitrary and Violative of Natural Justice. Writ Petition Maintainable Despite Arbitration Clause Under Article 226 of Constitution of India, as Termination Notices Dated 13.11.2025 and 02.12.2025...
Related Judgement
High Court Petition Seeking Quashing of FIR in Dowry Death Case Dismissed. Court holds that allegations of cruelty, dowry harassment, and suicide justify full investigation and trial