Supreme Court Allows Appeal Against Arbitrator Appointment in Tender Dispute Due to Absence of Concluded Contract. No Valid Arbitration Agreement Found as Letter of Intent Was Contingent on Formal Work Order Under Section 7 of Arbitration and Conciliation Act, 1996.

  • 10
Judgement Image
Font size:
Print

Case Note & Summary

The dispute arose between Maharashtra State Electricity Distribution Company Limited (MSEDCL), a state government electricity distribution utility, and Respondent, a partnership firm engaged in civil construction. MSEDCL floated a tender in August 2021 for civil and interior work estimated at ₹17.41 crore. The respondent participated, submitted bids and bank guarantees, and received a Letter of Intent (LOI) dated 16.11.2022 accepting their bid for ₹17.76 crore. However, no formal work order was issued despite repeated requests. The respondent terminated the contract in August 2024 citing failure to hand over sites, invoked arbitration under Clause 23 of the tender documents, and filed a Section 11 application before the Bombay High Court when MSEDCL refused arbitration. The High Court appointed an arbitrator ex-parte on 01.10.2025, finding a concluded contract existed through the LOI and correspondence. The core legal issue was whether a valid arbitration agreement existed between the parties under Section 7 of the Arbitration and Conciliation Act, 1996. MSEDCL argued no concluded contract existed as the LOI was contingent on a formal work order, and mere reference to tender documents did not incorporate the arbitration clause. They cited precedents including State of Himachal Pradesh v. OASYS Cybernatics and NBCC v. Zillion Infraprojects. The respondent argued the arbitration clause in tender documents, once accepted through the LOI and acted upon through bank guarantees, formed a valid arbitration agreement under Section 7(4)(b), and the arbitrator should decide jurisdictional issues under Section 16. The Supreme Court analyzed the limited scope of judicial scrutiny under Section 11(6A), referencing Vidya Drolia and SBI General Insurance cases. The court found the LOI was contingent, requiring a formal work order, and thus no concluded contract existed. Without a concluded contract, the arbitration clause in tender documents was not incorporated. The court held the appointment of arbitrator was unsustainable as there was no valid arbitration agreement. The appeal was allowed, setting aside the High Court's order and dismissing the Section 11 application.

Headnote

A) Arbitration Law - Arbitrator Appointment - Existence of Arbitration Agreement - Arbitration and Conciliation Act, 1996, Section 7 - High Court appointed arbitrator under Section 11 based on LOI and tender documents - Supreme Court held no concluded contract existed as LOI was contingent on formal work order - Without concluded contract, arbitration clause in tender documents not incorporated - Held appointment of arbitrator unsustainable (Paras 19-30).

B) Arbitration Law - Judicial Scrutiny - Scope of Section 11 Proceedings - Arbitration and Conciliation Act, 1996, Section 11(6A) - High Court examined correspondence and found arbitration agreement existed - Supreme Court applied limited scrutiny principle but found manifest absence of arbitration agreement - Held referral court must examine existence of arbitration agreement at threshold stage (Paras 20-22).

C) Contract Law - Formation of Contract - Letter of Intent as Contingent Document - Not mentioned - Appellant argued LOI was precursor to contract requiring formal work order - Supreme Court accepted LOI was contingent and did not create binding contract - Held mere reference to tender documents does not import arbitration clause without concluded contract (Paras 23-25).

D) Arbitration Law - Incorporation by Reference - Arbitration Clause in Tender Documents - Arbitration and Conciliation Act, 1996, Section 7 - Respondent argued arbitration clause in tender documents incorporated through LOI - Supreme Court held mere reference to another document insufficient without specific incorporation - Held arbitration agreement must be clearly discernible from documents (Paras 26-27).

Issue of Consideration: Whether, on a prima facie view, there exists an arbitration agreement between the parties and whether the reference to arbitration under Section 11 by the High Court warrants interference

Final Decision

Appeal allowed, impugned order of High Court set aside, application under Section 11 of Arbitration and Conciliation Act, 1996 dismissed

2026 LawText (SC) (04) 31

Civil Appeal No(s). of 2026 (Arising out of SLP (C) No. 36889 of 2025)

2026-04-09

J.K. MAHESHWARI J. , ATUL S. CHANDURKAR J.

2026 INSC 342

Mr. Vikas Singh, Mr. Abhijit A. Desai

Maharashtra State Electricity Distribution Company Limited (MSEDCL) & Ors.

R Z Malpani

Nature of Litigation: Appeal against High Court order appointing arbitrator under Section 11 of Arbitration and Conciliation Act, 1996

Remedy Sought

Appellant seeks quashing of arbitrator appointment, Respondent sought appointment of arbitrator

Filing Reason

High Court appointed arbitrator ex-parte based on finding of concluded contract and arbitration agreement

Previous Decisions

Bombay High Court appointed arbitrator on 01.10.2025 in Arbitration Application (L) No. 1417 of 2025

Issues

Whether, on a prima facie view, there exists an arbitration agreement between the parties Whether the reference to arbitration under Section 11 by the High Court warrants interference

Submissions/Arguments

Appellant argued no concluded contract existed, LOI was contingent, arbitration clause not incorporated Respondent argued arbitration clause in tender documents incorporated through LOI, arbitrator should decide jurisdiction under Section 16

Ratio Decidendi

No concluded contract existed as Letter of Intent was contingent on formal work order, therefore arbitration clause in tender documents not incorporated, no valid arbitration agreement under Section 7 of Arbitration and Conciliation Act, 1996

Judgment Excerpts

The instant appeal is directed against the judgment dated 01.10.2025 of the Bombay High Court By the impugned order, the High Court disposed of the application filed by the Respondent under Section 11 of the Arbitration and Conciliation Act, 1996 The short question which falls for our consideration in the instant appeal is whether, on a prima facie view, there exists an arbitration agreement between the parties The law on appointment of an arbitrator under Section 11 of the 1996 Act has undergone windfall change in the recent years

Procedural History

Tender floated on 11.08.2021, LOI issued on 16.11.2022, contract terminated on 05.08.2024, arbitration invoked on 30.08.2024, Section 11 application filed in 2025, High Court appointed arbitrator on 01.10.2025, Supreme Court appeal filed

Related Judgement
Supreme Court Supreme Court Allows Appeal Against Arbitrator Appointment in Tender Dispute Due to Absence of Concluded Contract. No Valid Arbitration Agreement Found as Letter of Intent Was Contingent on Formal Work Order Under Section 7 of Arbitration and Concili...
Related Judgement
Supreme Court Supreme Court Reverses NCLAT Decision on Corporate Insolvency Resolution Process Due to Pre-existing Dispute. The Court found that communications and actions by the corporate debtor prior to the demand notice under Section 8 of the Insolvency and Ban...