Bombay High Court Allows Arbitration Application Under Section 11 of Arbitration Act, Condoning 258-Day Delay. Court Appoints Sole Arbitrator to Adjudicate Partnership Disputes Arising from Deed of Alteration of Partnership Dated 10 April 2013.

High Court: Bombay High Court Bench: BOMBAY
  • 8
Judgement Image
Font size:
Print

Case Note & Summary

The applicant, Infra Poonam Developers LLP, filed an application under Section 11 of the Arbitration and Conciliation Act, 1996 for appointment of an arbitrator to resolve disputes arising from a Deed of Alteration of Partnership dated 10 April 2013. The application was filed with a delay of 258 days, and the applicant also filed an interim application for condonation of delay. The dispute pertains to a property known as Panwala chawl Nos. 2 and 3 in Mumbai, originally belonging to a private trust and acquired by M/s. R.B. Builders and Developers (the Firm) for redevelopment. The Firm had 7 partners initially, and later a nominee of the applicant, Poonam Infra, was added as an 8th partner with a 15% profit-sharing ratio. However, it was realized that a partnership firm cannot be a partner of another firm, so the Deed of Alteration of Partnership was executed on 10 April 2013, making the applicant itself the 8th partner. The redevelopment project faced issues, including a show cause notice from MHADA and litigation between the Society, Firm, and MHADA. The applicant sought arbitration to resolve disputes regarding the partnership and redevelopment. The court considered the submissions of both parties, including the respondent's opposition to the condonation of delay. The court found the explanation for the delay to be reasonable and condoned the delay. Consequently, the court allowed the arbitration application and appointed a sole arbitrator to adjudicate the disputes.

Headnote

A) Arbitration Law - Appointment of Arbitrator - Section 11 of the Arbitration and Conciliation Act, 1996 - Condonation of Delay - The applicant sought appointment of an arbitrator for disputes arising from a Deed of Alteration of Partnership dated 10 April 2013. The application was filed with a delay of 258 days. The court considered the explanation for delay and found it sufficient to condone. Held that the delay is condoned and an arbitrator is appointed to adjudicate the disputes between the parties (Paras 1-21).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the delay of 258 days in filing the arbitration application under Section 11 of the Arbitration and Conciliation Act, 1996 should be condoned and an arbitrator appointed.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The court condoned the delay of 258 days and allowed the arbitration application, appointing a sole arbitrator to adjudicate the disputes between the parties.

Law Points

  • Section 11 of the Arbitration and Conciliation Act
  • 1996
  • Limitation Act
  • 1963
  • Section 5 of the Limitation Act
  • Condonation of delay
  • Appointment of arbitrator
Subscribe to unlock Law Points Subscribe Now

Case Details

2026:BHC-OS:8327

Arbitration Application (L) No.37441 of 2025 with Interim Application (L) No.11418 of 2026

2026-04-07

Sandeep V. Marne, J.

2026:BHC-OS:8327

Mr. Aman Saraf with Ms. Sakshi Agarwal i/b. Mr. Bipin J. Joshi for the Applicant; Mr. Ziyad Madon with Mr. Chittesh Dalmia for Respondent No.6

Infra Poonam Developers LLP

Jasbir Singh s/o. Ajit Singh and Ors.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Application under Section 11 of the Arbitration and Conciliation Act, 1996 for appointment of an arbitrator to adjudicate disputes arising from a Deed of Alteration of Partnership.

Remedy Sought

Appointment of an arbitrator by the court.

Filing Reason

Disputes between the parties regarding the partnership and redevelopment of the suit property.

Issues

Whether the delay of 258 days in filing the arbitration application should be condoned. Whether an arbitrator should be appointed under Section 11 of the Arbitration and Conciliation Act, 1996.

Submissions/Arguments

Applicant argued that the delay was due to bona fide reasons and should be condoned. Respondent opposed the condonation of delay.

Ratio Decidendi

The court found the explanation for the delay to be sufficient and condoned it, thereby allowing the appointment of an arbitrator under Section 11 of the Arbitration and Conciliation Act, 1996.

Judgment Excerpts

This is an Application filed by the Applicant under Section 11 of the Arbitration and Conciliation Act, 1996 for appointment of an Arbitrator for adjudication of disputes between the parties arising out of Deed of Alteration of Partnership dated 10 April 2013. Since there is delay of 258 days in filing the Application, the Applicant has filed Interim Application (L) No.11418 of 2026 for condonation thereof.

Procedural History

The applicant filed Arbitration Application (L) No.37441 of 2025 under Section 11 of the Arbitration and Conciliation Act, 1996 on an unspecified date. The application was delayed by 258 days, leading to the filing of Interim Application (L) No.11418 of 2026 for condonation of delay. The court heard both applications and pronounced judgment on 7 April 2026.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 11
  • Limitation Act, 1963: Section 5
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Allows Arbitration Application Under Section 11 of Arbitration Act, Condoning 258-Day Delay. Court Appoints Sole Arbitrator to Adjudicate Partnership Disputes Arising from Deed of Alteration of Partnership Dated 10 April 2013.
Related Judgement
Supreme Court Supreme Court Decides Teacher Recruitment Dispute Involving Termination and Natural Justice. Case Involves SEBC (Women) Category Appointment Under 1996 Resolution and Tribunal Orders on Reinstatement.