Supreme Court Allows Appeals in Power Purchase Agreement Dispute — Fixed Costs Payable Irrespective of Energy Purchase. HERC Order Set Aside as Tariff Commission's Final Order Binding on Parties Under Section 86(1)(f) of Electricity Act, 2003.

  • 27
Judgement Image
Font size:
Print

Case Note & Summary

The appeals arose from an Appellate Tribunal for Electricity (APTEL) order dated 23.03.2012, which upheld the Haryana Electricity Regulatory Commission (HERC) order dated 23.03.2010. The dispute involved a Power Purchase Agreement (PPA) dated 12.08.1998 between Haryana Power Purchase Centre (appellant) and Magnum Power Generation Limited (respondent). The PPA provided for a tariff of Rs. 2.40 per kWh, with a fixed component of Rs. 1.29 per unit and a variable component. The HERC, in a tariff order dated 12.08.2003, allowed fixed costs to be paid to the generator irrespective of whether any energy was purchased. This order was not challenged by either party. Subsequently, the appellant filed a petition under Section 86(1)(f) of the Electricity Act, 2003, seeking recovery of dues. The HERC, in its order dated 23.03.2010, dismissed the appellant's claim and directed that any excess recovery from consumers be refunded. APTEL upheld this order. The Supreme Court allowed the appeals, holding that the HERC's tariff order dated 12.08.2003 was final and binding, and the Commission could not disregard it in subsequent proceedings. The court set aside the orders of HERC and APTEL and directed that the fixed costs be paid as per the tariff order.

Headnote

A) Electricity Law - Power Purchase Agreement - Fixed Cost - Tariff Order Binding - The HERC's final tariff order dated 12.08.2003, which allowed fixed costs to the generator irrespective of energy purchase, was binding on the parties and could not be overridden in subsequent proceedings under Section 86(1)(f) of the Electricity Act, 2003. The court held that the Commission's earlier order was final and not challenged, thus the fixed cost component had to be paid. (Paras 1-8)

B) Electricity Law - Section 86(1)(f) - Dispute Resolution - Scope - The jurisdiction under Section 86(1)(f) does not permit reopening of a final tariff order that has attained finality. The court held that the HERC's order dated 23.03.2010, which effectively denied fixed costs, was contrary to its own earlier order and was set aside. (Paras 7-8)

C) Contract Law - Power Purchase Agreement - Interpretation - Clause 8.2 and Schedule 4 - The PPA provided for payment of fixed cost (Rs. 1.29 per unit) as part of tariff up to 75% PLF, and the tariff order recognized that fixed cost must be paid even if no energy is purchased. The court upheld this interpretation. (Paras 4-6)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the Haryana Electricity Regulatory Commission (HERC) could, in proceedings under Section 86(1)(f) of the Electricity Act, 2003, disregard its own final tariff order dated 12.08.2003 which mandated payment of fixed costs to the generator irrespective of energy purchase, and whether the Appellate Tribunal for Electricity (APTEL) erred in upholding such disregard.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Supreme Court allowed the appeals, set aside the orders of APTEL dated 23.03.2012 and HERC dated 23.03.2010, and directed that the fixed costs be paid to the appellant as per the tariff order dated 12.08.2003.

Law Points

  • Fixed cost payable irrespective of energy purchase
  • Tariff order binding on parties
  • Section 86(1)(f) Electricity Act
  • 2003
  • Power Purchase Agreement interpretation
  • Plant Load Factor
  • Availability Declaration
  • Generation Schedule
Subscribe to unlock Law Points Subscribe Now

Case Details

2020 LawText (SC) (1) 34

Civil Appeal Nos. 4407-4408 of 2011 and Civil Appeal Nos. 7446-7447 of 2012

2020-01-21

R.F. Nariman

Haryana Power Purchase Centre

Magnum Power Generation Limited & Anr.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Civil appeals against orders of APTEL and HERC regarding payment of fixed costs under a Power Purchase Agreement.

Remedy Sought

Appellant sought setting aside of HERC and APTEL orders and direction for payment of fixed costs as per tariff order.

Filing Reason

Dispute over payment of fixed costs under PPA; HERC order dated 23.03.2010 dismissed appellant's claim despite earlier tariff order allowing fixed costs.

Previous Decisions

HERC tariff order dated 12.08.2003 allowed fixed costs irrespective of energy purchase; HERC order dated 23.03.2010 dismissed appellant's claim; APTEL order dated 23.03.2012 upheld HERC order.

Issues

Whether the HERC could disregard its own final tariff order in proceedings under Section 86(1)(f) of the Electricity Act, 2003. Whether fixed costs under the PPA are payable irrespective of energy purchase.

Submissions/Arguments

Appellant argued that the tariff order dated 12.08.2003 was final and binding, and fixed costs must be paid. Respondent argued that the HERC order dated 23.03.2010 was correct and that fixed costs were not payable if no energy was purchased.

Ratio Decidendi

A final tariff order of the Regulatory Commission is binding on the parties and cannot be overridden in subsequent dispute resolution proceedings under Section 86(1)(f) of the Electricity Act, 2003. Fixed costs under a PPA are payable irrespective of whether energy is purchased, as per the tariff order.

Judgment Excerpts

The Commission then held as follows:- 'The Commission has not allowed any power to be sourced from Magnum. However, against the volume of 160 MUs proposed by the licensee the fixed cost at the rate of Rs. 1.29 per unit is being allowed.' This Tariff Order which binds both parties was a final order, not being challenged by either party.

Procedural History

PPA dated 12.08.1998; HERC tariff order dated 12.08.2003; HERC order dated 23.03.2010 under Section 86(1)(f); APTEL order dated 23.03.2012 upholding HERC; Supreme Court appeals filed.

Acts & Sections

  • Electricity Act, 2003: 86(1)(f)
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Allows Appeals in Power Purchase Agreement Dispute — Fixed Costs Payable Irrespective of Energy Purchase. HERC Order Set Aside as Tariff Commission's Final Order Binding on Parties Under Section 86(1)(f) of Electricity Act, 2003.
Related Judgement
Supreme Court Supreme Court Dismisses State's Appeal in Pension Dispute Under Indian Forest Service Pay Rules. The Court Held That the Principle of Equal Pay for Equal Work Does Not Apply to Grant Pension Benefits Based on an Upgraded Post to a Retired Officer, as...