Supreme Court Modifies Interest Rate to 9% in Consumer Disputes Against Developer for Delayed Possession. The Court upheld deficiency in service but reduced interest from 15% to 9% per annum, following earlier precedent in Himanshu Arora case.

  • 4
Judgement Image
Font size:
Print

Case Note & Summary

The Supreme Court disposed of a batch of appeals arising from consumer complaints against DLF Homes Panchkula (P) Ltd. regarding its residential project 'DLF Valley, Panchkula' in Haryana. The developer had promised to hand over possession of apartments within 24 months from the signing of the agreement, but failed to do so, leading to complaints before the State Consumer Disputes Redressal Commission, Chandigarh. The State Commission allowed the complaints, directing refund of amounts deposited with interest at 15% per annum in some cases and compensation for delayed possession. The developer appealed to the National Consumer Disputes Redressal Commission, which affirmed the State Commission's orders and dismissed the appeals. The developer then approached the Supreme Court. Meanwhile, some complainants also filed appeals challenging the National Commission's order staying its judgment due to a High Court stay. The Supreme Court noted that in a similar batch of appeals (Himanshu Arora case), it had directed interest at 9% per annum instead of the higher rates awarded by the lower fora. The parties agreed to dispose of the present appeals on similar terms. The Court directed that in refund cases, interest at 9% per annum be paid from the date of deposit till refund. In possession cases, no compensation was payable for the first three years (including the original two-year period and one-year extension), and thereafter interest at 9% per annum was payable on the deposited amount for the delay period. For transferred allotments, the interest computation was adjusted accordingly. The Court directed the developer to file a chart of calculations, which was appended as Annexure-A, and ordered that the amounts deposited in court be transferred to the State Commission for disbursement after verification. The appeals were disposed of in terms of the modified directions.

Headnote

A) Consumer Law - Deficiency in Service - Delay in Possession - The developer failed to deliver possession of apartments within the stipulated period of 24 months, constituting deficiency in service under the Consumer Protection Act, 1986 - The court upheld the finding of deficiency but modified the interest rate to 9% per annum in line with earlier directions in Himanshu Arora case (Paras 3-10).

B) Consumer Law - Interest Rate - Refund Cases - In refund cases, interest at 9% per annum is payable on deposits from the date of deposit till the date of refund - This modification was agreed upon by both parties to ensure uniformity (Paras 9-10).

C) Consumer Law - Interest Rate - Possession Cases - In cases where possession is sought, no compensation is payable for the first three years from the date of agreement (including the original two-year period and one-year extension) - Thereafter, interest at 9% per annum is payable on the deposited amount for the period of delay (Paras 9-10).

D) Consumer Law - Transfer of Allotment - Subsequent Purchaser - Where a subsequent purchaser steps into the shoes of the original allottee, the interest in refund cases is computed from the date of transfer for amounts deposited by the original allottee, and from the date of subsequent deposits by the transferee - In possession cases, compensation runs from the later of three years from the agreement or the date of transfer (Paras 9-10).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the National Commission was justified in affirming the State Commission's orders directing refund with interest at 15% per annum and compensation for delayed possession, and whether the interest rate should be modified in light of earlier Supreme Court directions.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Supreme Court disposed of the appeals with the following directions: (a) In refund cases, interest at 9% per annum is payable on deposits from the date of deposit till the date of refund. (b) In possession cases, no compensation is payable for the first three years from the date of agreement; thereafter, interest at 9% per annum is payable on the deposited amount for the delay period. (c) For transferred allotments, interest is computed from the date of transfer for amounts deposited by the original allottee, and from the date of subsequent deposits by the transferee. The amounts deposited in court shall be transferred to the State Commission for disbursement after verification. The appeals are disposed of in terms of the modified directions.

Law Points

  • Consumer Protection Act
  • 1986
  • Interest rate
  • Refund
  • Possession
  • Compensation
  • Delay in possession
  • Deficiency in service
Subscribe to unlock Law Points Subscribe Now

Case Details

2019 LawText (SC) (2) 164

Civil Appeal Nos. 2285-2330 of 2019 (Arising out of SLP(C) Nos. 928-930, 932-938, 940-967 and 969-976 of 2019) and connected matters

2019-02-20

Uday Umesh Lalit, J.

DLF Homes Panchkula (P) Ltd. Through its Authorised Signatory Mr. Shiv Kumar

Sushila Devi and Anr. etc.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Consumer appeals against orders of the National Consumer Disputes Redressal Commission affirming State Commission's directions for refund with interest and compensation for delayed possession of apartments.

Remedy Sought

The developer sought reduction of interest rate and modification of compensation; some complainants sought enforcement of higher interest and possession.

Filing Reason

The developer failed to deliver possession of apartments within the stipulated 24 months, leading to complaints of deficiency in service.

Previous Decisions

State Commission allowed complaints directing refund with interest at 15% per annum in some cases and compensation for delayed possession; National Commission affirmed these orders and dismissed developer's appeals.

Issues

Whether the National Commission was correct in affirming the State Commission's orders directing refund with interest at 15% per annum? Whether the interest rate should be modified to 9% per annum in line with the Supreme Court's directions in Himanshu Arora case? What should be the period for which interest is payable in refund and possession cases?

Submissions/Arguments

The developer argued that the interest rate of 15% per annum was excessive and should be reduced to 9% as per the Supreme Court's earlier order in Himanshu Arora case. The complainants agreed to the modification of interest rate to 9% per annum but sought clarity on the period of computation and treatment of transferred allotments.

Ratio Decidendi

In consumer disputes involving delayed possession of apartments, the appropriate rate of interest for refund and compensation is 9% per annum, and no compensation is payable for the period of three years from the date of agreement (including the original two-year period and one-year extension) in possession cases.

Judgment Excerpts

The Developer had promised to handover possession within 24 months from the date of signing of the agreement. We, therefore, directed the Developer to file a Chart in consultation with all the complainants and indicate what modalities be adopted. In all Refund cases, the award of interest @ 9% would be payable in respect of deposits from the day they were made till the date of refund. In cases where Possession was sought, the period available to the Developer under the agreement being three years ... ought not to be computed while calculating compensation in the form of interest.

Procedural History

Complaints filed before State Consumer Disputes Redressal Commission, Chandigarh, which allowed them with interest at 15% per annum. Developer appealed to National Consumer Disputes Redressal Commission, which affirmed the orders. Developer then filed special leave petitions in the Supreme Court. Meanwhile, some complainants also filed appeals. The Supreme Court disposed of the appeals with modified directions on interest rate.

Acts & Sections

  • Consumer Protection Act, 1986:
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Modifies Interest Rate to 9% in Consumer Disputes Against Developer for Delayed Possession. The Court upheld deficiency in service but reduced interest from 15% to 9% per annum, following earlier precedent in Himanshu Arora case.
Related Judgement
Supreme Court Supreme Court Allows Secured Creditor's Winding Up Petition Despite DRT Decree — Recovery of Debts Act Does Not Bar Winding Up Proceedings Under Companies Act. Secured Creditor Need Not Relinquish Security Before Admission of Winding Up Petition; E...