Case Note & Summary
The Supreme Court partly allowed appeals by claimants seeking enhanced compensation for land acquired for the Hirehalla project. The Government notified the land on 16.10.2003 for rehabilitating Veerapur villagers. The Land Acquisition Officer awarded Rs.24,500 per acre, which the Reference Court raised to Rs.1,26,500 per acre. The High Court further enhanced it to Rs.1,56,000 per acre by applying 5% escalation from a 1994 notification. The claimants appealed, arguing for higher compensation. The Supreme Court condoned the significant delay in filing (2154 and 2109 days) citing liberal approach in land acquisition matters, relying on Imrat Lal and Dhiraj Singh. On merits, the Court considered the land's potential for development as it was acquired for rehabilitation (non-agricultural use) and applied 10% cumulative escalation per annum from 1994 to 2003, arriving at Rs.2,35,795 per acre. However, the Court denied interest on the enhanced compensation for the delay period. The appeals were partly allowed with no order as to costs.
Headnote
A) Land Acquisition - Condonation of Delay - Section 5 of Limitation Act, 1963 - Liberal approach in land acquisition matters - Court condoned delay of 2154 days and 2109 days in filing SLPs, holding that villagers are often illiterate and delay should not defeat just compensation - Relied on Imrat Lal v. Land Acquisition Collector and Dhiraj Singh v. State of Haryana (Paras 5-7). B) Land Acquisition - Market Value Determination - Escalation Rate - Potential for Development - Agricultural land acquired for rehabilitation (non-agricultural use) - Court granted 10% cumulative escalation per annum from 1994 to 2003, considering potential for development as building sites - Relied on General Manager, ONGC v. Rameshbhai Jivanbhai Patel (Paras 8-9). C) Land Acquisition - Interest on Enhanced Compensation - Denial for Delay - Claimants not entitled to interest on enhanced compensation for the period of delay in filing and refiling SLPs - Equities balanced by denying interest (Para 10).
Issue of Consideration
Whether the delay in filing the special leave petition should be condoned to consider the claim for enhanced compensation, and what should be the appropriate escalation rate for market value of agricultural land acquired for rehabilitation.
Final Decision
Appeals partly allowed; compensation enhanced to Rs.2,35,795 per acre; claimants not entitled to interest on enhanced compensation for the period of delay in filing and refiling SLPs; no order as to costs.
Law Points
- Condonation of delay in land acquisition matters
- escalation of market value for potential development
- denial of interest for delayed filing



