Case Note & Summary
The appeal arose from a judgment of the High Court of Delhi that deferred the execution of a consent award dated 01.03.2019, rendered by the Singapore International Arbitration Centre in Arbitration No. 093/2017. The appellants, had entered into a share purchase agreement with the respondents, promoters of Rockland Hospitals Limited (renamed Medeor). Disputes under this agreement were settled through a deed of compromise dated 02.02.2019, which was incorporated into the consent award. The award included Paragraph 32(a), wherein the promoters agreed to defend specified litigation, including an arbitration claim by Ernst and Young LLP against Medeor for Rs. 10 crore, and to ensure no liability is recovered from the appellants, with a provision to discharge any confirmed liability within 30 days after the highest court of appeal's decision. Subsequently, an award dated 17.08.2021 was issued in favor of Ernst and Young, which Medeor challenged under Section 34 of the Arbitration and Conciliation Act, 1996, with a stay granted subject to deposit. The appellants sought enforcement of the consent award under Section 36, arguing the promoters' obligation was immediate, while the respondents contended it arose only after final confirmation by the highest court of appeal. The High Court dismissed the enforcement petition as premature, interpreting the indemnity clause under Sections 124 and 125 of the Indian Contract Act, 1872, to require payment only upon such confirmation. On appeal, the Supreme Court heard arguments from both sides, with the appellants emphasizing the commercial intent and immediacy of protection, and the respondents focusing on contractual wording. The Court analyzed the consent award as an indemnity contract, referencing Khetarpal Amarnath v. Madhukar Pictures to hold that liability can accrue upon loss, not just final adjudication. It performed a harmonious construction of Paragraph 32(a), finding that the clause aimed to shield the appellants from any recovery, including interim deposits, with the 'highest court of appeal' reference setting a payment deadline rather than a condition for all obligations. The Court concluded that the enforcement was not premature, as the promoters' duty to ensure no liability is recovered was ongoing and enforceable, and allowed the appeal, directing execution of the consent award.
Headnote
A) Arbitration Law - Enforcement of Consent Awards - Section 36 Arbitration and Conciliation Act, 1996 - The Supreme Court considered the enforceability of a consent award arising from a deed of compromise that settled disputes under a share purchase agreement. The award included an indemnity clause where promoters agreed to defend litigation and ensure no liability is recovered from the appellants. The Court analyzed whether enforcement was premature given pending challenges to the underlying liability award. Held that the consent award is enforceable as it creates immediate obligations, and the indemnity clause does not defer liability until final confirmation by the highest court of appeal, emphasizing commercial intent and protection against interim liabilities. (Paras 2-13) B) Contract Law - Indemnity Contracts - Sections 124, 125 Indian Contract Act, 1872 - The dispute centered on interpreting Paragraph 32(a) of the consent award as an indemnity contract. The High Court had viewed it as requiring payment only after liability confirmation by the highest court of appeal, but the Supreme Court disagreed. Applying principles from Khetarpal Amarnath v. Madhukar Pictures, the Court held that an indemnifier's liability can arise as soon as a loss accrues, not necessarily upon final adjudication. The clause's wording, including 'ensure no liability is recovered,' indicated an immediate obligation to protect against any recovery, including interim deposits. (Paras 11, 13) C) Contract Law - Interpretation of Contracts - Harmonious Construction - The Court addressed ambiguity in Paragraph 32(a), which contained conflicting parts on timing of liability discharge. Rejecting the High Court's narrow reading, the Supreme Court applied harmonious construction to align the clause with the commercial purpose of the deed of compromise. It interpreted 'Highest Court of Appeal' contextually, not as a condition precedent for all obligations, but as specifying the deadline for payment after final confirmation, while interim protections remain enforceable. This ensured the indemnity's effectiveness throughout litigation. (Paras 11, 13)
Premium Content
The Headnote is only available to subscribed members.
Subscribe Now to access key legal points
Issue of Consideration: Whether the enforcement of a consent award, which includes an indemnity clause, is premature when the liability it covers is under challenge and not yet confirmed by the highest court of appeal, and the correct interpretation of the indemnity obligation's timing.
Premium Content
The Issue of Consideration is only available to subscribed members.
Subscribe Now to access critical case issues
Final Decision
Supreme Court allowed the appeal, set aside the impugned judgment, and directed execution of the consent award, holding that the indemnity obligation is immediate and enforceable.




