Supreme Court Allows CIDCO's Appeal Against Quashing of Additional Lease Premium Demand. High Court's Direction to Issue 'No Dues Certificate' Set Aside as Respondent No.3 Failed to Establish Timely Completion of Construction.

  • 12
Judgement Image
Font size:
Print

Case Note & Summary

The Supreme Court allowed the appeal filed by City & Industrial Development Corporation of Maharashtra Ltd. (CIDCO) against the order of the Bombay High Court. The dispute arose from the allotment of a plot by CIDCO to M/s Mehak Developers Pvt. Ltd. (respondent No.3) under a lease agreement dated 04.08.1995, governed by the New Bombay Disposal of Land Regulations, 1975. The lessee was required to complete construction within a stipulated time, failing which additional lease premium would be payable retrospectively from 06.08.2001. The lessee completed 'A' Wing by 31.12.2005 but sought extension for 'B' Wing, which was granted up to 31.12.2008. The lessee claimed construction was completed by 24.12.2008, but CIDCO contended that only a completion certificate was created, not actual completion. CIDCO issued a demand letter dated 20.04.2016/01.07.2016 for Rs.14,05,60,587/- towards additional lease premium. Respondents No.1 and 2, who purchased 'B' Wing under a sale deed dated 16.06.2011, challenged this demand in the High Court, seeking a 'No Dues Certificate' to obtain an occupancy certificate. The High Court quashed the demand and directed CIDCO to issue the certificate. The Supreme Court held that respondents No.1 and 2 had limited locus to challenge the demand as it affected their right to occupancy, but they could not establish the fact of timely completion of construction, which was the lessee's burden. The Court found that the lessee had not challenged the demand, and the High Court had not given CIDCO an opportunity to verify completion. The Supreme Court set aside the High Court's order and remanded the matter for fresh consideration, allowing CIDCO to file a counter affidavit and the lessee to establish completion. The appeal was allowed with no order as to costs.

Headnote

A) Civil Procedure - Locus Standi - Subsequent Purchaser - Privity of Contract - A subsequent purchaser of a building, though not in privity of contract with the lessor, has limited locus to challenge a demand for additional lease premium if the demand affects their right to obtain an occupancy certificate, but cannot contest the factual completion of construction within the time frame, which is a matter for the original lessee to establish. (Paras 8-9)

B) Property Law - Lease - Additional Lease Premium - Completion of Construction - Undertaking - Under the New Bombay Disposal of Land Regulations, 1975, Regulations 6 and 7, a lessee who fails to complete construction within the extended time is liable to pay additional lease premium retrospectively from the original due date, as per the undertaking given. The burden of proving timely completion lies on the lessee. (Paras 10-12)

C) Constitutional Law - Writ Jurisdiction - High Court's Power - The High Court erred in quashing the demand for additional lease premium and directing issuance of 'No Dues Certificate' without giving the appellant an opportunity to verify the completion of construction, especially when the lessee had not challenged the demand. The matter requires reconsideration by the High Court. (Paras 13-18)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the High Court was justified in quashing the demand for additional lease premium and directing issuance of 'No Dues Certificate' when the construction was allegedly not completed within the extended time, and whether the respondents No.1 and 2 had locus to challenge the demand.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Supreme Court allowed the appeal, set aside the High Court order dated 29.08.2018, and remanded the matter to the High Court for fresh consideration. The High Court was directed to permit the appellant to file a counter affidavit and the respondent No.3 to establish completion of construction within the extended time. The interim order passed by this Court shall continue until the High Court disposes of the petition. No order as to costs.

Law Points

  • Locus standi of subsequent purchaser
  • Privity of contract
  • Additional lease premium
  • Completion of construction
  • Undertaking
  • New Bombay Disposal of Land Regulations
  • 1975
Subscribe to unlock Law Points Subscribe Now

Case Details

2019 LawText (SC) (11) 101

Civil Appeal No. 8443 of 2019 (Arising out of SLP (Civil) No.8864 of 2019)

2019-11-06

A.S. Bopanna

Mr. Ajit S. Bhasme (for appellant), Mr. Shyam Divan (for respondents No.1 and 2), Mr. V. Giri (for respondent No.3), Mr. Suhas Kadam (for respondent No.4)

City & Industrial Development Corporation of Maharashtra Ltd.

Lambda Therapeutic Research Ltd. & Ors.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Civil appeal against High Court order quashing demand for additional lease premium and directing issuance of 'No Dues Certificate'.

Remedy Sought

Appellant CIDCO sought to set aside the High Court order and uphold the demand for additional lease premium.

Filing Reason

Appellant aggrieved by High Court order quashing its demand for Rs.14,05,60,587/- towards additional lease premium and directing issuance of 'No Dues Certificate'.

Previous Decisions

High Court of Judicature at Bombay in W.P.No.12674 of 2017 quashed the demand and directed issuance of 'No Dues Certificate'.

Issues

Whether respondents No.1 and 2 had locus standi to challenge the demand for additional lease premium. Whether the construction of 'B' Wing was completed within the extended time period (31.12.2008) so as to avoid additional lease premium. Whether the High Court was justified in quashing the demand and directing issuance of 'No Dues Certificate'.

Submissions/Arguments

Appellant: No privity of contract between appellant and respondents No.1 and 2; respondents No.1 and 2 had no locus to challenge the demand; construction was not completed within time; demand was justified. Respondents No.1 and 2: They were bona fide purchasers for valuable consideration; they had interest in the property; the demand affected their right to obtain occupancy certificate; construction was completed before 31.12.2008. Respondent No.3: Supported respondents No.1 and 2; contended that construction was completed within time.

Ratio Decidendi

A subsequent purchaser of a building has limited locus to challenge a demand for additional lease premium if it affects their right to obtain an occupancy certificate, but cannot establish the fact of timely completion of construction, which is the burden of the original lessee. The High Court erred in quashing the demand without giving the lessor an opportunity to verify completion, especially when the lessee had not challenged the demand.

Judgment Excerpts

The High Court having considered the matter has quashed the demand made through the impugned letter dated 20.04.2016/01.07.2016 and has directed the appellant herein to issue ‘No dues Certificate’. The appellant contends that the respondent No.3 was, therefore, liable to pay the additional lease premium retrospectively from 06.08.2001 and as such the communication dated 20.04.2016/01.07.2016 was issued to respondent No.3 which is in accordance with the terms of allotment. The respondents No.1 and 2, to the limited extent can be considered as aggrieved persons for examination of their contention to the limited extent. The contentions to indicate that the construction was completed before 31.12.2008 and that respondent No.3 is therefore not liable to pay the amount indicated in the impugned communication cannot however be accepted at the instance of respondents No.1 and 2 since the fact of completion of construction within the time frame is to be established by respondent No. 3 alone.

Procedural History

The appellant CIDCO issued a demand letter dated 20.04.2016/01.07.2016 to respondent No.3 for additional lease premium. Respondents No.1 and 2 filed W.P.No.12674 of 2017 before the Bombay High Court challenging the demand. The High Court quashed the demand and directed issuance of 'No Dues Certificate' on 29.08.2018. CIDCO appealed to the Supreme Court by way of SLP (Civil) No.8864 of 2019, which was converted into Civil Appeal No.8443 of 2019.

Acts & Sections

  • New Bombay Disposal of Land Regulations, 1975: Regulations 6, 7
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Allows CIDCO's Appeal Against Quashing of Additional Lease Premium Demand. High Court's Direction to Issue 'No Dues Certificate' Set Aside as Respondent No.3 Failed to Establish Timely Completion of Construction.
Related Judgement
Supreme Court Supreme Court Upholds High Court's Reversal in Gift Deed Case: Presumption of Acceptance Arises from Recital of Possession Delivery. Gift to a deity is validly accepted by trustees; unilateral cancellation by donor is void.