Bombay High Court Allows Petitioner's Petition for Extension of Bank Guarantee Pending Challenge to Arbitral Award — Section 9 of Arbitration and Conciliation Act, 1996. Post-award interim protection can be granted under Section 9 to preserve the subject matter of arbitration pending challenge to award.

High Court: Bombay High Court Bench: BOMBAY In Favour of Prosecution
  • 5
Judgement Image
Font size:
Print

Case Note & Summary

The petitioner, Oil and Natural Gas Corporation Limited (ONGC), filed a petition under Section 9 of the Arbitration and Conciliation Act, 1996, seeking continuation and extension of a bank guarantee furnished by the respondent, Swiber Offshore Construction Pte. Limited (Swiber), pending adjudication of ONGC's challenge to the arbitral award dated 30 September 2025. The dispute arose from a commercial contract between the parties, and the arbitral tribunal had passed an award. ONGC challenged the award under Section 34 of the Act. During the pendency of the challenge, the bank guarantee was due to expire. ONGC sought interim relief to prevent the guarantee from lapsing, arguing that without such protection, the award would become unenforceable. The respondent opposed, contending that Section 9 could not be invoked post-award. The court analyzed the scope of Section 9 and held that it applies even after the award is passed, as long as the proceedings are pending. The court noted that the purpose of Section 9 is to preserve the subject matter of the arbitration and ensure effective enforcement of the award. Accordingly, the court allowed the petition and directed the respondent to extend the bank guarantee until the disposal of the challenge petition. The court emphasized that the power under Section 9 is discretionary and must be exercised to prevent frustration of the arbitral process.

Headnote

A) Arbitration Law - Post-Award Interim Relief - Section 9 of the Arbitration and Conciliation Act, 1996 - Extension of Bank Guarantee - The petitioner sought continuation of a bank guarantee furnished by the respondent pending challenge to the arbitral award. The court held that Section 9 empowers the court to grant interim measures even after the award is passed, to preserve the subject matter of the arbitration and ensure that the award does not become a paper victory. The court directed the respondent to extend the bank guarantee until the disposal of the challenge petition. (Paras 1-2)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the court can grant post-award interim protection under Section 9 of the Arbitration and Conciliation Act, 1996, by directing extension of a bank guarantee pending adjudication of a challenge to the arbitral award.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The court allowed the petition and directed the respondent to extend the bank guarantee until the disposal of the challenge petition.

Law Points

  • Post-award interim protection under Section 9 of the Arbitration and Conciliation Act
  • 1996
  • Extension of bank guarantee pending challenge to arbitral award
  • Scope of Section 9 post-award
Subscribe to unlock Law Points Subscribe Now

Case Details

2026 LawText (BOM) (06) 50

Commercial Arbitration Petition No. 17832 of 2026

2026-06-15

Amit Borkar

Zubin Behramkamdin, Shreya Gupta, Abhijeet Sadikale, Sanjana Kattoor i/b Shardul Amarchand Mangaldas & Co. for the petitioner; Venkatesh Dhond, Vinodini Srinivasan, Ganesh Chandru, Siddhart Agrawal, Dharmesh S Jain, Shashwat Dhyani, Arpita Tiwari i/b Anil T. Agarwal for the respondent

Oil and Natural Gas Corporation Limited

Swiber offshore Construction PTE Limited

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Commercial arbitration petition seeking post-award interim protection under Section 9 of the Arbitration and Conciliation Act, 1996.

Remedy Sought

ONGC sought continuation and extension of a bank guarantee furnished by Swiber pending adjudication of ONGC's challenge to the arbitral award.

Filing Reason

The bank guarantee was due to expire, and ONGC feared that without extension, the award would become unenforceable.

Previous Decisions

An arbitral award was passed on 30 September 2025. ONGC challenged the award under Section 34 of the Act.

Issues

Whether Section 9 of the Arbitration and Conciliation Act, 1996, can be invoked post-award to seek interim protection pending challenge to the award.

Submissions/Arguments

ONGC argued that Section 9 applies even after the award is passed to preserve the subject matter of arbitration. Swiber contended that Section 9 cannot be used post-award.

Ratio Decidendi

Section 9 of the Arbitration and Conciliation Act, 1996, empowers the court to grant interim measures even after the award is passed, pending challenge to the award, to preserve the subject matter of arbitration and ensure effective enforcement.

Judgment Excerpts

The present petition raises an issue concerning the scope of post award interim protection under Section 9 of the Arbitration and Conciliation Act, 1996. The petitioner, Oil and Natural Gas Corporation Limited (ONGC), seeks continuation and extension of a bank guarantee furnished by the respondent, Swiber Offshore Construction Pte. Limited (Swiber), pending adjudication of ONGC's challenge to the arbitral award dated 30 September 2025.

Procedural History

The arbitral award was passed on 30 September 2025. ONGC challenged the award under Section 34 of the Act. During the pendency of the challenge, ONGC filed the present petition under Section 9 seeking extension of the bank guarantee.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 9
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court High Court Allows Writ Petition, Quashes Revenue Orders in Land Dispute, Upholds Civil Decree and Will-Based Transfer Under Gujarat Land Revenue Code
Related Judgement
High Court Bombay High Court Allows Petitioner's Petition for Extension of Bank Guarantee Pending Challenge to Arbitral Award — Section 9 of Arbitration and Conciliation Act, 1996. Post-award interim protection can be granted under Section 9 to preserve the s...