Case Note & Summary
The dispute arose from a contract dated 05.02.1985 between Chandigarh Construction Co. Pvt. Ltd. (claimant) and the State of Punjab (opposite party) for construction of the Sutlej Yamuna Link Canal. The contract amount was Rs.59,86,732/- with an estimated cost of Rs.31 lakhs. During execution, the scope of work increased due to various factors, leading the claimant to seek additional payment. The matter was referred to arbitration under the Arbitration Act, 1940. The Arbitrator passed an award on 31.08.1994, allowing most claims including Claim No.2 for premium at 93.12% on extra work, and granting interest at 18% per annum. The opposite party filed objections, and the Trial Court modified the award by rejecting Claim No.1 and reducing interest to 12%. Both parties appealed. The First Appellate Court allowed the opposite party's appeal, setting aside Claims No.2, 3, 8, 12, and 16, and dismissed the claimant's cross-appeal. The High Court in revision restored Claim No.1 but affirmed the rejection of the other claims. The claimant appealed to the Supreme Court. The Supreme Court examined the contractual requirement under Clause 63 that awards of Rs.1 lakh and above must state reasons. The Arbitrator's award on Claim No.2 merely stated 'As per agreement premium works out to 93.12% which is awarded' without detailed reasoning. However, the Court found that the premium rate was evident from the contract documents (estimated cost Rs.31 lakhs vs. contract amount Rs.59,86,732/-), and thus the award was sustainable. The Court restored the Arbitrator's award on Claims No.2, 3, and 12. Regarding Claim No.8 for extra payment in swampy area, the Court noted that the Arbitrator had not considered the time-bar issue, and the lower courts did not examine the evidence. Hence, the Court remitted Claim No.8 to the High Court for fresh consideration. On interest, the Court upheld the reduction to 12% per annum as reasonable. The appeal was partly allowed.
Headnote
A) Arbitration Law - Reasoned Award - Contractual Requirement - Clause 63 of Contract - The contract required that awards of Rs.1 lakh and above must state reasons. The Arbitrator's award on Claim No.2 merely stated 'As per agreement premium works out to 93.12% which is awarded' without any reasoning. The Supreme Court held that this was insufficient compliance with the contractual requirement, but since the premium rate was evident from the contract documents (estimated cost Rs.31 lakhs, contract amount Rs.59,86,732/- yielding 93.12% premium), the award on Claim No.2 was sustainable. The Court restored the Arbitrator's award on Claims No.2, 3, and 12. (Paras 9-14) B) Arbitration Law - Extra Work - Time-Barred Claim - Claim No.8 for extra payment in swampy area (DALDAL) - The First Appellate Court and High Court rejected the claim on the ground that it was not made within the time stipulated in the contract. The Supreme Court found that the Arbitrator had not considered this aspect and the courts below did not examine the evidence. The Court remitted Claim No.8 to the High Court for fresh consideration. (Paras 15-17) C) Arbitration Law - Interest - Rate of Interest - The Arbitrator awarded 18% per annum, which was reduced to 12% by the Trial Court and affirmed by the High Court. The Supreme Court upheld the reduction to 12% per annum, noting that the rate was reasonable and in line with prevailing rates. (Paras 18-19)
Issue of Consideration
Whether the Arbitrator's award of premium at 93.12% for extra work under Claim No.2 (and consequential Claims No.3 and 12) was sustainable despite lack of detailed reasons, and whether Claim No.8 for extra payment in swampy area was correctly rejected for being time-barred, and whether the interest rate of 12% per annum was appropriate.
Final Decision
Appeal partly allowed. The Supreme Court restored the Arbitrator's award on Claims No.2, 3, and 12. Claim No.8 is remitted to the High Court for fresh consideration. The interest rate of 12% per annum as reduced by the Trial Court is upheld. The judgment of the High Court is set aside to the extent indicated.
Law Points
- Arbitration Award
- Reasoned Award
- Contractual Requirement
- Premium Rate
- Extra Work
- Interest
- Remand



