Supreme Court Upholds Regulatory Commission's Order Restricting Depreciation to Actual Supply Period in Electricity Tariff Dispute. Depreciation under Regulation 6.32 of DERC (Terms and Conditions for Determination of Generation Tariff) Regulations, 2011 cannot be allowed beyond the period of actual supply of electricity to consumers, as consumer interest is paramount under Section 61(d) of the Electricity Act, 2003.

  • 21
Judgement Image
Font size:
Print

Case Note & Summary

The Supreme Court allowed the appeal filed by the Delhi Electricity Regulatory Commission (Commission) against the judgment of the Appellate Tribunal for Electricity (APTEL). The dispute arose from the setting up of a temporary 108-megawatts gas-based power plant at Rithala, Delhi, by Tata Power Delhi Distribution Limited (TPDDL) to augment power supply for the Commonwealth Games 2010. The plant was approved with an operational tenure limited to 5-6 years, and the Power Purchase Agreement (PPA) restricted supply up to March 2018. The Commission, by order dated 31.08.2017, determined the capital cost at ₹197.70 crores and allowed the plant to operate only till March 2018. Subsequently, in a true-up petition, the Commission allowed depreciation only up to Financial Year 2017-2018, resulting in cumulative depreciation of ₹83.34 crores, and disallowed recovery of the remaining capital cost of approximately ₹94.59 crores on the ground that the plant had ceased to supply electricity after March 2018. APTEL set aside this order, directing that the entire capital cost be recovered through depreciation over the useful life of 15 years. The Supreme Court framed three substantial questions of law: whether depreciation must be allowed over the entire technical useful life irrespective of actual supply; whether Regulation 6.32 confers an absolute right to recover capital cost over useful life even if the asset ceases to supply; and whether APTEL erred in disregarding the regulatory framework limiting the operational period to six years. The Court answered the first question in the negative, holding that consumers cannot be required to pay for electricity not supplied. On the second question, the Court held that Regulation 6.32 must be read harmoniously with Regulation 4.1, which mandates tariff determination in accordance with the PPA. The Court found that APTEL erred in disregarding the approved PPA period and the regulatory framework. The Court set aside the APTEL judgment and restored the Commission's order dated 11.11.2019, thereby allowing the appeal.

Headnote

A) Electricity Law - Tariff Determination - Depreciation - Section 61(d), Section 62, Electricity Act, 2003; Regulation 6.32, DERC (Terms and Conditions for Determination of Generation Tariff) Regulations, 2011 - Depreciation must be allowed only for the period during which electricity is actually supplied to consumers - The Supreme Court held that consumers cannot be required to pay for a service they no longer receive, and the regulatory framework must balance cost recovery with consumer interest (Paras 19-20).

B) Electricity Law - Interpretation of Regulations - Harmonious Construction - Regulation 6.32 read with Regulation 4.1, DERC (Terms and Conditions for Determination of Generation Tariff) Regulations, 2011 - Regulation 6.32 must be read harmoniously with Regulation 4.1, which mandates tariff determination in accordance with the Power Purchase Agreement - The Court held that depreciation cannot be claimed beyond the period approved in the PPA (Paras 21-22).

C) Electricity Law - Consumer Protection - Section 61(d), Electricity Act, 2003 - Consumer interest is a central guiding principle in tariff determination - The Court held that safeguarding consumers' interests is paramount and utilities cannot burden consumers with charges for electricity not supplied (Paras 15, 20).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether depreciation under tariff regulations must be allowed over entire technical useful life of an asset irrespective of actual period of supply; whether Regulation 6.32 confers absolute right to recover capital cost over useful life even if asset ceases to supply electricity; whether APTEL erred in disregarding regulatory framework limiting operational period to six years

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

Appeal allowed. Impugned judgment of APTEL dated 10.02.2025 set aside. Order of Delhi Electricity Regulatory Commission dated 11.11.2019 restored. No order as to costs.

Law Points

  • Depreciation allowed only for period of actual supply
  • Regulation 6.32 must be read with Regulation 4.1
  • Consumer interest paramount under Section 61(d) of Electricity Act
  • 2003
  • Tariff cannot be recovered for electricity not supplied
Subscribe to unlock Law Points Subscribe Now

Case Details

2026 LawText (SC) (05) 16

Civil Appeal No. 6388 of 2025

2026-05-07

PAMIDIGHANTAM SRI NARASIMHA J. , ALOK ARADHE J.

2026 INSC 461

Delhi Electricity Regulatory Commission

Tata Power Delhi Distribution Limited

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Civil appeal under Section 125 of the Electricity Act, 2003 against judgment of Appellate Tribunal for Electricity (APTEL) setting aside order of Delhi Electricity Regulatory Commission regarding depreciation recovery for a power plant.

Remedy Sought

Appellant (Commission) sought setting aside of APTEL judgment and restoration of its order dated 11.11.2019 restricting depreciation to period of actual supply.

Filing Reason

Dispute over whether depreciation on capital cost of a power plant can be recovered over its entire useful life of 15 years when the plant ceased to supply electricity after 6 years.

Previous Decisions

Commission order dated 31.08.2017 determined capital cost and restricted operation to 6 years; Commission order dated 11.11.2019 allowed depreciation only up to FY 2017-2018; APTEL order dated 10.02.2025 set aside Commission order and directed recovery over 15 years.

Issues

Whether depreciation under tariff regulations must be allowed over entire technical useful life irrespective of actual supply period. Whether Regulation 6.32 of 2011 Regulations confers absolute right to recover capital cost over useful life even if asset ceases to supply electricity. Whether APTEL erred in disregarding regulatory framework and approval conditions limiting operational and recovery period to six years.

Submissions/Arguments

Appellant (Commission): TPDDL cannot recover capital cost for electricity not supplied; consumers cannot be burdened beyond March 2018; APTEL misapplied Regulation 6.32. Respondent (TPDDL): Entitled to depreciation under Regulation 6.32 which does not restrict to operational life; seeking balance recovery of depreciable capital cost; Commission must implement APTEL directions.

Ratio Decidendi

Depreciation under tariff regulations must be allowed only for the period during which electricity is actually supplied to consumers. Regulation 6.32 of the 2011 Regulations must be read harmoniously with Regulation 4.1, which mandates tariff determination in accordance with the Power Purchase Agreement. Consumer interest is paramount under Section 61(d) of the Electricity Act, 2003, and consumers cannot be required to pay for electricity not supplied.

Judgment Excerpts

The consumers cannot be required to pay for a service which they no longer received. Regulation 6.32 of 2011 Regulations must be construed harmoniously with Regulation 4.1 of 2011 Regulations. Section 61(d) specifically provides that in specifying the terms and conditions for the determination of tariff, the Appropriate Commission shall be guided, inter alia, by the object of safeguarding consumers’ interests and at the same time, recovery of the cost of electricity in a reasonable manner.

Procedural History

Commission order dated 31.08.2017 determined capital cost and restricted operation to 6 years. Commission order dated 11.11.2019 allowed depreciation only up to FY 2017-2018. TPDDL appealed to APTEL. APTEL order dated 10.02.2025 set aside Commission order and directed recovery over 15 years. Commission appealed to Supreme Court under Section 125 of Electricity Act, 2003.

Acts & Sections

  • Electricity Act, 2003: Section 61, Section 61(d), Section 62, Section 86(1)(b), Section 125
  • Code of Civil Procedure, 1908: Section 100
  • DERC (Terms and Conditions for Determination of Generation Tariff) Regulations, 2011: Regulation 4.1, Regulation 6.30, Regulation 6.31, Regulation 6.32
  • DERC (Treatment of Income from Other Business of Transmission Licensee and Distribution Licensee) Regulations, 2005:
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Upholds Regulatory Commission's Order Restricting Depreciation to Actual Supply Period in Electricity Tariff Dispute. Depreciation under Regulation 6.32 of DERC (Terms and Conditions for Determination of Generation Tariff) Regulations, ...
Related Judgement
Supreme Court Supreme Court Allows Appeal Against Arbitrator Appointment in Tender Dispute Due to Absence of Concluded Contract. No Valid Arbitration Agreement Found as Letter of Intent Was Contingent on Formal Work Order Under Section 7 of Arbitration and Concili...