Case Note & Summary
The Supreme Court of India heard an appeal by Maharashtra State Electricity Distribution Company Limited (MSEDCL) against an order of the Appellate Tribunal for Electricity (APTEL) which had upheld an order of the Maharashtra State Electricity Regulatory Commission (MERC). MERC had quashed several circulars issued by MSEDCL's predecessor, the Maharashtra State Electricity Board (MSEB), between 1998 and 2001, which imposed 'take or pay' obligations and minimum offtake requirements on holders of captive power plants (CPPs). The circulars also provided for standby power and penal charges. MERC held that these circulars required its approval under the Electricity Regulatory Commissions Act, 1998, and since no approval was obtained, they were invalid. MERC directed MSEDCL to refund amounts collected under these circulars to the respondent consumers. The dispute arose when respondent no.3, M/s. NRC Ltd., which had set up a CPP, sought reduction in contract demand and challenged the circulars. The High Court had relegated the matter to MERC, which then quashed the circulars. The Supreme Court examined the chronology: the Electricity Regulatory Commissions Act, 1998 came into force on 25.4.1998, but MERC was constituted only on 5.8.1999. The first two circulars (dated 23.7.1998 and 25.5.1999) were issued before MERC's constitution. The Court noted that under the Electricity Supply Act, 1948, the Board had the power to frame tariffs and conditions of supply, including for CPPs. The Government of Maharashtra had issued a resolution on 20.12.1997 empowering the Board to finalise arrangements. The Court observed that MERC itself had earlier stated that CPP policy was a policy matter under the jurisdiction of the State Government, and its silence on the policy in tariff orders could not be taken as disapproval. The Court held that MERC could not quash circulars issued before its constitution for want of its approval, and that the order imposing a huge refund liability of Rs.504 crores without considering the financial viability of MSEDCL was unsustainable. The Supreme Court allowed the appeal, set aside the orders of MERC and APTEL, and directed that the circulars be treated as valid until prospectively modified by MERC, with no refund liability.
Headnote
A) Electricity Law - Captive Power Plant Policy - Retrospective Quashing of Circulars - Electricity Regulatory Commissions Act, 1998, Sections 22, 43 - MERC quashed circulars issued by MSEB from 1998 onwards on the ground that they were not approved by MERC, even though MERC was constituted only on 5.8.1999 - Supreme Court held that circulars issued before MERC's constitution did not require its approval, and MERC's order imposing refund liability of Rs.504 crores without considering financial impact was unsustainable - Held that the Commission should have applied the principle of prospective overruling and considered the financial viability of the appellant (Paras 1, 15, 17, 18). B) Electricity Law - Take or Pay Obligation - Minimum Offtake Requirement - Electricity Supply Act, 1948, Sections 49, 79(j) - The Board was empowered to impose 'take or pay' obligation and minimum offtake requirement on captive power plant holders under its tariff-making power - The circulars were part of the Board's policy and were submitted to MERC for approval, but MERC's silence in earlier tariff orders could not be construed as disapproval - Held that the Board's actions were within its statutory powers and the circulars were valid until set aside prospectively (Paras 5, 8, 9, 13). C) Electricity Law - Financial Viability - Refund Liability - Electricity Act, 2003, Section 62 - MERC's order directing refund of amounts collected under the circulars imposed a huge financial burden of Rs.504 crores on the appellant, which was not financially sound - Supreme Court held that the Commission must consider the financial impact of its orders and cannot impose retrospective liability that would render the utility financially unviable - Held that the order of refund was unsustainable and set aside (Paras 1, 18).
Issue of Consideration
Whether the Maharashtra State Electricity Regulatory Commission (MERC) could quash circulars issued by the Maharashtra State Electricity Board (MSEB) regarding captive power plant policy retrospectively, and whether such circulars required prior approval of MERC when issued before MERC's constitution.
Final Decision
The Supreme Court allowed the appeal, set aside the orders of MERC dated 21.5.2004 and APTEL dated 30.5.2007. The Court held that the circulars issued before MERC's constitution did not require its approval, and MERC's order imposing refund liability without considering financial viability was unsustainable. The circulars were to be treated as valid until prospectively modified by MERC, and no refund was to be made.
Law Points
- Electricity Regulatory Commission cannot quash pre-existing circulars retrospectively without considering financial viability
- Captive Power Plant policy is within domain of State Government
- Approval of Commission not required for circulars issued before its constitution
- Doctrine of prospective overruling applies to regulatory orders imposing financial burden



