Supreme Court Allows Appeal of Electricity Distribution Company Against Quashing of Captive Power Plant Circulars. MERC's Retrospective Quashing of Pre-Approval Circulars Without Considering Financial Impact Set Aside.

  • 2
Judgement Image
Font size:
Print

Case Note & Summary

The Supreme Court of India heard an appeal by Maharashtra State Electricity Distribution Company Limited (MSEDCL) against an order of the Appellate Tribunal for Electricity (APTEL) which had upheld an order of the Maharashtra State Electricity Regulatory Commission (MERC). MERC had quashed several circulars issued by MSEDCL's predecessor, the Maharashtra State Electricity Board (MSEB), between 1998 and 2001, which imposed 'take or pay' obligations and minimum offtake requirements on holders of captive power plants (CPPs). The circulars also provided for standby power and penal charges. MERC held that these circulars required its approval under the Electricity Regulatory Commissions Act, 1998, and since no approval was obtained, they were invalid. MERC directed MSEDCL to refund amounts collected under these circulars to the respondent consumers. The dispute arose when respondent no.3, M/s. NRC Ltd., which had set up a CPP, sought reduction in contract demand and challenged the circulars. The High Court had relegated the matter to MERC, which then quashed the circulars. The Supreme Court examined the chronology: the Electricity Regulatory Commissions Act, 1998 came into force on 25.4.1998, but MERC was constituted only on 5.8.1999. The first two circulars (dated 23.7.1998 and 25.5.1999) were issued before MERC's constitution. The Court noted that under the Electricity Supply Act, 1948, the Board had the power to frame tariffs and conditions of supply, including for CPPs. The Government of Maharashtra had issued a resolution on 20.12.1997 empowering the Board to finalise arrangements. The Court observed that MERC itself had earlier stated that CPP policy was a policy matter under the jurisdiction of the State Government, and its silence on the policy in tariff orders could not be taken as disapproval. The Court held that MERC could not quash circulars issued before its constitution for want of its approval, and that the order imposing a huge refund liability of Rs.504 crores without considering the financial viability of MSEDCL was unsustainable. The Supreme Court allowed the appeal, set aside the orders of MERC and APTEL, and directed that the circulars be treated as valid until prospectively modified by MERC, with no refund liability.

Headnote

A) Electricity Law - Captive Power Plant Policy - Retrospective Quashing of Circulars - Electricity Regulatory Commissions Act, 1998, Sections 22, 43 - MERC quashed circulars issued by MSEB from 1998 onwards on the ground that they were not approved by MERC, even though MERC was constituted only on 5.8.1999 - Supreme Court held that circulars issued before MERC's constitution did not require its approval, and MERC's order imposing refund liability of Rs.504 crores without considering financial impact was unsustainable - Held that the Commission should have applied the principle of prospective overruling and considered the financial viability of the appellant (Paras 1, 15, 17, 18).

B) Electricity Law - Take or Pay Obligation - Minimum Offtake Requirement - Electricity Supply Act, 1948, Sections 49, 79(j) - The Board was empowered to impose 'take or pay' obligation and minimum offtake requirement on captive power plant holders under its tariff-making power - The circulars were part of the Board's policy and were submitted to MERC for approval, but MERC's silence in earlier tariff orders could not be construed as disapproval - Held that the Board's actions were within its statutory powers and the circulars were valid until set aside prospectively (Paras 5, 8, 9, 13).

C) Electricity Law - Financial Viability - Refund Liability - Electricity Act, 2003, Section 62 - MERC's order directing refund of amounts collected under the circulars imposed a huge financial burden of Rs.504 crores on the appellant, which was not financially sound - Supreme Court held that the Commission must consider the financial impact of its orders and cannot impose retrospective liability that would render the utility financially unviable - Held that the order of refund was unsustainable and set aside (Paras 1, 18).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the Maharashtra State Electricity Regulatory Commission (MERC) could quash circulars issued by the Maharashtra State Electricity Board (MSEB) regarding captive power plant policy retrospectively, and whether such circulars required prior approval of MERC when issued before MERC's constitution.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Supreme Court allowed the appeal, set aside the orders of MERC dated 21.5.2004 and APTEL dated 30.5.2007. The Court held that the circulars issued before MERC's constitution did not require its approval, and MERC's order imposing refund liability without considering financial viability was unsustainable. The circulars were to be treated as valid until prospectively modified by MERC, and no refund was to be made.

Law Points

  • Electricity Regulatory Commission cannot quash pre-existing circulars retrospectively without considering financial viability
  • Captive Power Plant policy is within domain of State Government
  • Approval of Commission not required for circulars issued before its constitution
  • Doctrine of prospective overruling applies to regulatory orders imposing financial burden
Subscribe to unlock Law Points Subscribe Now

Case Details

2020 LawText (SC) (2) 51

Civil Appeal No. 4304 of 2007

2020-02-28

Arun Mishra

Maharashtra State Electricity Distribution Co. Ltd.

Union of India and Others

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Civil appeal against order of Appellate Tribunal for Electricity dismissing appeal against MERC order quashing circulars imposing take or pay obligation and minimum offtake requirement on captive power plant holders.

Remedy Sought

Appellant MSEDCL sought setting aside of MERC and APTEL orders and validation of its circulars.

Filing Reason

MERC quashed circulars issued by MSEB from 1998 onwards on the ground that they were not approved by MERC, and directed refund of amounts collected.

Previous Decisions

MERC order dated 21.5.2004 quashed circulars; APTEL order dated 30.5.2007 dismissed appeal against MERC order.

Issues

Whether MERC could quash circulars issued before its constitution for want of its approval? Whether the circulars imposing 'take or pay' obligation and minimum offtake requirement were within the powers of MSEB under the Electricity Supply Act, 1948? Whether MERC's order directing refund without considering financial viability of MSEDCL was sustainable?

Submissions/Arguments

Appellant argued that CPP policy was within domain of State Government, circulars were issued under powers under Electricity Supply Act, 1948, and MERC's approval was not required for circulars issued before its constitution. MERC's earlier orders had stated that CPP policy was a policy matter and its silence could not be taken as disapproval. Respondents argued that circulars required approval of MERC under the Electricity Regulatory Commissions Act, 1998, and since no approval was obtained, they were invalid. MERC had the power to quash them retrospectively.

Ratio Decidendi

An Electricity Regulatory Commission cannot quash circulars issued before its constitution for want of its approval, and any order imposing retrospective financial liability must consider the financial viability of the utility. The principle of prospective overruling applies to regulatory orders that impose significant financial burdens.

Judgment Excerpts

The Commission is of the opinion that the 'Captive Power Policy' is a policy matter under the jurisdiction of the Government of Maharashtra... The Commission's silence on this policy should not be taken as approval of the same. The financial condition of the appellant MSEDCL is not sound enough to sustain such kind of liability for refund.

Procedural History

MSEB issued circulars from 1998 to 2001 regarding CPP policy. Respondent nos.3 to 7 filed petitions before MERC challenging the circulars. MERC, by order dated 21.5.2004, quashed the circulars and directed refund. MSEDCL appealed to APTEL, which dismissed the appeal on 30.5.2007. MSEDCL then appealed to the Supreme Court by way of Civil Appeal No. 4304 of 2007.

Acts & Sections

  • Electricity Regulatory Commissions Act, 1998: 22, 43
  • Electricity Supply Act, 1948: 44, 49, 59, 79(j)
  • Electricity Act, 2003: 62
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Allows Appeal of Electricity Distribution Company Against Quashing of Captive Power Plant Circulars. MERC's Retrospective Quashing of Pre-Approval Circulars Without Considering Financial Impact Set Aside.
Related Judgement
Supreme Court Supreme Court Allows Appeals in UPTET Eligibility Dispute: Candidates Pursuing TTC Can Appear in TET. Pursuing Teacher Training Course Satisfies Eligibility Condition Under NCTE Guidelines for Teacher Eligibility Test.