Supreme Court Allows Appeals Against Appointment of Arbitrator in WAPCOS Ltd. v. Salma Dam Joint Venture. The court held that the arbitration agreement was novated by a subsequent amendment and that the petitioner lacked authority to invoke arbitration after revocation of power of attorney.

  • 7
Judgement Image
Font size:
Print

Case Note & Summary

The Supreme Court of India heard appeals against the Delhi High Court's order appointing a sole arbitrator under Section 11(6) of the Arbitration and Conciliation Act, 1996. The dispute arose from a contract for the Salma Dam Project in Afghanistan, where WAPCOS Ltd. (a public sector undertaking) was the employer and Salma Dam Joint Venture (SDJV) was the contractor. SDJV was a joint venture between SSJV Projects Pvt. Ltd. (SSPPL) and Angelique International Ltd. (AIL), with SSPPL as lead partner holding 95% share. The original contract dated 09.03.2006 contained an arbitration clause (Clause 20.6 of CoPA). Later, on 09.06.2015, the parties executed an Amendment of Agreement (AoA) which provided for a Technical Committee to resolve disputes, replacing the earlier arbitration mechanism. After disputes arose, AIL revoked the Power of Attorney granted to SSPPL on 21.09.2016, and communicated this to WAPCOSL. Despite this, SSPPL unilaterally invoked arbitration on behalf of SDJV on 12.11.2016 and filed a petition under Section 11(6) on 15.12.2016. The High Court allowed the petition, holding that the arbitration agreement was still in force and SSPPL had authority. The Supreme Court reversed, holding that the AoA novated the original contract, extinguishing the arbitration clause, and that SSPPL lacked authority after revocation of the Power of Attorney. The appeals were allowed, and the High Court's order was set aside.

Headnote

A) Arbitration Law - Existence of Arbitration Agreement - Novation - The arbitration agreement in the Contract Agreement dated 09.03.2006 was novated by the Amendment of Agreement dated 09.06.2015, which provided a different dispute resolution mechanism through a Technical Committee, thereby extinguishing the original arbitration clause. The court held that the arbitration agreement was not subsisting on the date of filing the petition under Section 11(6) of the Arbitration and Conciliation Act, 1996. (Paras 19-25)

B) Arbitration Law - Authority to Invoke Arbitration - Revocation of Power of Attorney - SSPPL, as lead partner of SDJV, had authority under the Joint Venture Agreement and Power of Attorney to invoke arbitration, but AIL revoked the Power of Attorney on 21.09.2016, communicated before the petition was filed on 15.12.2016. The court held that the petition filed by SSPPL after revocation was not validly presented, as SSPPL lacked authority to represent SDJV. (Paras 26-30)

C) Arbitration Law - Section 11(6) Petition - Locus Standi - The petition under Section 11(6) of the Arbitration and Conciliation Act, 1996, filed by SSPPL on behalf of SDJV, was not maintainable because the arbitration agreement had been novated and SSPPL's authority had been revoked. The court set aside the High Court's order appointing an arbitrator. (Paras 31-35)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the arbitration agreement in the Contract Agreement dated 09.03.2006 was subsisting on the date of filing the arbitration petition, and whether the petition filed by SSPPL on behalf of SDJV was valid despite revocation of authority by AIL.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Supreme Court allowed the appeals, set aside the High Court's order dated 25.01.2019, and dismissed the arbitration petition filed by SDJV through SSPPL under Section 11(6) of the Arbitration and Conciliation Act, 1996.

Law Points

  • Arbitration agreement novation
  • Authority to invoke arbitration
  • Revocation of power of attorney
  • Section 11(6) Arbitration and Conciliation Act
  • 1996
  • Joint venture representation
Subscribe to unlock Law Points Subscribe Now

Case Details

2019 LawText (SC) (11) 11

Civil Appeal No. of 2019 (Arising out of SLP (C) No. 7979 of 2019) and Civil Appeal No. of 2019 (Arising out of SLP (C) No. of 2019) (Diary No. 6975 of 2019)

2019-11-14

A.M. Khanwilkar

Gaurav Panchnanda, Shyam Divan, Sachin Datta

WAPCOS Ltd. and Angelique International Ltd.

Salma Dam Joint Venture & Anr.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Civil appeals against High Court order appointing arbitrator under Section 11(6) of the Arbitration and Conciliation Act, 1996.

Remedy Sought

Setting aside the High Court's order appointing a sole arbitrator.

Filing Reason

Dispute over whether the arbitration agreement was subsisting and whether SSPPL had authority to invoke arbitration on behalf of SDJV after revocation of Power of Attorney by AIL.

Previous Decisions

High Court of Delhi allowed the arbitration petition and appointed a sole arbitrator on 25.01.2019. Earlier, the Supreme Court had set aside a previous High Court order dated 15.03.2017 and remanded the matter.

Issues

Whether the arbitration agreement in the Contract Agreement dated 09.03.2006 was subsisting on the date of filing the arbitration petition (15.12.2016) given the Amendment of Agreement dated 09.06.2015. Whether the arbitration petition filed by SSPPL on behalf of SDJV was validly presented despite the revocation of authority by AIL on 21.09.2016.

Submissions/Arguments

WAPCOSL argued that the Amendment of Agreement novated the original contract, extinguishing the arbitration clause, and that SSPPL lacked authority after revocation of Power of Attorney. AIL argued that it did not consent to SSPPL's unilateral invocation of arbitration and that the petition was not maintainable. SDJV argued that the arbitration agreement was still in force and that SSPPL had authority under the Joint Venture Agreement and Power of Attorney.

Ratio Decidendi

The Amendment of Agreement dated 09.06.2015 novated the original contract, including the arbitration clause, and provided a different dispute resolution mechanism. Additionally, the revocation of the Power of Attorney by AIL on 21.09.2016, communicated before the petition was filed, meant that SSPPL lacked authority to represent SDJV in invoking arbitration or filing the Section 11(6) petition.

Judgment Excerpts

The arbitration agreement in the Contract Agreement dated 09.03.2006 was novated by the Amendment of Agreement dated 09.06.2015, which provided a different dispute resolution mechanism through a Technical Committee, thereby extinguishing the original arbitration clause. SSPPL lacked authority to invoke arbitration on behalf of SDJV after the revocation of the Power of Attorney by AIL on 21.09.2016, which was communicated before the petition was filed on 15.12.2016.

Procedural History

The dispute arose from a contract for the Salma Dam Project. After disputes, SSPPL invoked arbitration on behalf of SDJV on 12.11.2016. WAPCOSL objected. SSPPL filed a petition under Section 11(6) before the Delhi High Court, which appointed an arbitrator on 15.03.2017. WAPCOSL appealed to the Supreme Court, which set aside the order on 11.12.2017 and remanded. The High Court again appointed an arbitrator on 25.01.2019. WAPCOSL and AIL appealed to the Supreme Court, which allowed the appeals and set aside the High Court's order.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 11(6), Section 9
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Allows Appeals Against Appointment of Arbitrator in WAPCOS Ltd. v. Salma Dam Joint Venture. The court held that the arbitration agreement was novated by a subsequent amendment and that the petitioner lacked authority to invoke arbitrati...
Related Judgement
Supreme Court Supreme Court Dismisses Appeal in Specific Performance Suit — Time Was Essence of Contract and Plaintiffs Failed to Prove Readiness and Willingness. Limitation Period Under Article 54 of Limitation Act, 1963 Starts from Date Fixed for Performance; ...