Supreme Court Allows Contractor's Appeal in ONGC Arbitration Dispute. Levy of Liquidated Damages Under Clause 2 of Contract Held Arbitrable, Not an Excepted Matter.

  • 5
Judgement Image
Font size:
Print

Case Note & Summary

The Supreme Court of India heard two civil appeals arising from a judgment of the Delhi High Court Division Bench, which had set aside an arbitral award and the Single Judge's order upholding it. The dispute involved a contract between M/s. Mitra Guha Builders (India) Company (appellant-contractor) and Oil and Natural Gas Corporation Limited (ONGC) (respondent) for construction of residential flats. The contractor completed the work with delays, and ONGC levied liquidated damages under Clause 2 of the contract. The contractor invoked arbitration under Clause 25, and the sole Arbitrator allowed the contractor's claims and disallowed ONGC's counterclaim for liquidated damages, holding that the levy was a penalty and that ONGC was substantially responsible for the delay. ONGC challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996, but the Single Judge dismissed the petitions. ONGC then appealed under Section 37, and the Division Bench reversed, holding that the levy of liquidated damages was an 'excepted matter' under Clause 2 read with Clause 25 and thus not arbitrable. The Supreme Court considered whether the levy of liquidated damages was an 'excepted matter' and whether the Arbitrator had jurisdiction. The Court held that Clause 2 does not expressly exclude the dispute from arbitration, and Clause 25 provides for arbitration of all disputes. The Court found that the Division Bench erred in reappreciating evidence and in holding that the levy was not a counter-blast. The Supreme Court restored the Arbitrator's award and the Single Judge's order, allowing the appeals.

Headnote

A) Arbitration Law - Arbitrability of Liquidated Damages - Excepted Matters - Clause 2 read with Clause 25 of Contract - The dispute pertained to whether the levy of liquidated damages by the Superintending Engineer under Clause 2 of the contract was an 'excepted matter' excluded from arbitration. The Supreme Court held that the levy of liquidated damages is not an 'excepted matter' and is arbitrable, as Clause 2 does not expressly exclude it from arbitration and Clause 25 provides for arbitration of all disputes. (Paras 1-10)

B) Contract Law - Liquidated Damages vs. Penalty - Section 74 of the Indian Contract Act, 1872 - The Arbitrator found that the liquidated damages claimed by ONGC were in the nature of penalty, as the delay was substantially attributable to ONGC. The Supreme Court upheld the Arbitrator's finding that the levy was not justified. (Paras 11-15)

C) Arbitration Law - Scope of Appellate Jurisdiction under Section 37 of the Arbitration and Conciliation Act, 1996 - The Division Bench of the High Court erred in reappreciating evidence and setting aside the Arbitrator's award and the Single Judge's order. The Supreme Court restored the award, holding that the Division Bench exceeded its jurisdiction under Section 37. (Paras 16-20)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the levy of liquidated damages by the Superintending Engineer under Clause 2 of the contract is an 'excepted matter' and thus not arbitrable.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

Appeals allowed; impugned judgment of Division Bench set aside; award of Arbitrator and order of Single Judge restored

Law Points

  • Arbitrability of liquidated damages
  • Excepted matters in arbitration
  • Interpretation of arbitration clauses
  • Section 34 and Section 37 of Arbitration and Conciliation Act
  • 1996
Subscribe to unlock Law Points Subscribe Now

Case Details

2019 LawText (SC) (11) 13

Civil Appeal No.5511 of 2012 with Civil Appeal No.5512 of 2012

2019-11-08

R. Banumathi

Bipin Prabhat for appellant, K.M. Natraj (ASG) for respondent

M/s. Mitra Guha Builders (India) Company

Oil and Natural Gas Corporation Limited

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Civil appeals against High Court judgment setting aside arbitral award

Remedy Sought

Appellant sought restoration of arbitral award allowing its claims and disallowing ONGC's liquidated damages

Filing Reason

High Court Division Bench held levy of liquidated damages was an 'excepted matter' not arbitrable

Previous Decisions

Arbitrator allowed contractor's claims and disallowed ONGC's liquidated damages; Single Judge upheld award; Division Bench set aside award

Issues

Whether levy of liquidated damages under Clause 2 is an 'excepted matter' and not arbitrable Whether the Arbitrator had jurisdiction to adjudicate on liquidated damages

Submissions/Arguments

Appellant: Clause 2 does not exclude levy of liquidated damages from arbitration; Clause 25 covers all disputes Respondent: Clause 2 makes Superintending Engineer's decision final; levy is an 'excepted matter' not arbitrable

Ratio Decidendi

The levy of liquidated damages under Clause 2 of the contract is not an 'excepted matter' and is arbitrable under Clause 25. The Arbitrator had jurisdiction to adjudicate on the levy, and the Division Bench erred in holding otherwise.

Judgment Excerpts

The Division Bench set aside the findings of the award passed by the learned Arbitrator and the order of the learned Single Judge by holding that Clause 2 of the agreement provided that the decision of the Superintending Engineer on the question of levy of liquidated damages is final and that the same could not have been agitated in the arbitration proceeding. The learned Single Judge held that when the respondent-ONGC themselves are responsible for substantive part of the delay, it can hardly be said that respondent is entitled to recovery of liquidated damages or penalty.

Procedural History

Contract between appellant and respondent dated 05.01.1996; disputes arose; arbitration invoked on 07.09.2001; Arbitrator appointed on 03.01.2002; award dated 01.07.2005; ONGC filed petitions under Section 34 dismissed by Single Judge on 02.11.2007; ONGC appealed under Section 37; Division Bench set aside award on 16.02.2009; appellant appealed to Supreme Court.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 34, Section 37
  • Indian Contract Act, 1872: Section 74
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Allows Contractor's Appeal in ONGC Arbitration Dispute. Levy of Liquidated Damages Under Clause 2 of Contract Held Arbitrable, Not an Excepted Matter.
Related Judgement
Supreme Court Supreme Court Reduces Disqualification Period for Delayed Submission of Election Expenses Under Maharashtra Village Panchayats Act — Proportionality of Penalty Considered